Texas energy projects waiting for approval
550 projects currently waiting on a permitting decision in Texas, tracked live from public federal and state sources. See every state →
550
Projects
205,258 MW
Capacity waiting
117,560 MW
Clean energy capacity waiting
285/550 projects are zero-carbon generation
$273.41B
Est. investment waiting
463/550 projects have an applicable estimate
Documented estimates, not precise figures. See methodology.
550 projects
| Project | Fuel | Location | Waiting ↓ | Capacity | Stage | Queue stage |
|---|---|---|---|---|---|---|
| Interconnection Request 18INR0009 (Gas) | Gas | TX | 11.4 yrs | 1,174 MW | Interconnection study | Facility Study |
| Interconnection Request 17INR0043 (Wind) | Wind (onshore) | TX | 10.4 yrs | 400 MW | Interconnection study | Facility Study |
| Interconnection Request 19INR0075 (Solar) | Solar | TX | 9.2 yrs | 301 MW | Interconnection study | Facility Study |
| Interconnection Request 20INR0233 (Wind) | Wind (onshore) | TX | 7.7 yrs | 282 MW | Interconnection study | Facility Study |
| Interconnection Request 21INR0294 (Solar) | Solar | TX | 7.4 yrs | 332 MW | Interconnection study | Facility Study |
| Interconnection Request 22INR0218 (Solar+Battery) | Solar | TX | 7.3 yrs | 252 MW | Interconnection study | Facility Study |
| Interconnection Request 21INR0380 (Solar+Battery) | Solar | TX | 7.1 yrs | 262 MW | Interconnection study | Facility Study |
| Interconnection Request 22INR0237 (Solar+Battery) | Solar | TX | 6.8 yrs | 411 MW | Interconnection study | Facility Study |
| Interconnection Request 23INR0008 (Solar+Battery) | Solar | TX | 6.7 yrs | 506 MW | Interconnection study | Facility Study |
| Interconnection Request 23INR0006 (Solar) | Solar | TX | 6.6 yrs | 255 MW | Interconnection study | Facility Study |
| SPS Interconnection Request GEN-2020-067 (Wind) | Wind (onshore) | TX | 6.4 yrs | 353 MW | Interconnection study | Facility Study |
| Interconnection Request 22INR0330 (Solar+Battery) | Solar | TX | 6.4 yrs | 303 MW | Interconnection study | Facility Study |
| Interconnection Request 22INR0332 (Battery) | Storage | TX | 6.4 yrs | 302 MW | Interconnection study | Facility Study |
| Interconnection Request 22INR0347 (Battery) | Storage | TX | 6.3 yrs | 302 MW | Interconnection study | Facility Study |
| Interconnection Request 22INR0337 (Solar) | Solar | TX | 6.3 yrs | 610 MW | Interconnection study | Facility Study |
| Interconnection Request 22INR0365 (Battery) | Storage | TX | 6.2 yrs | 307 MW | Interconnection study | Facility Study |
| ENTERGY TEXAS, INC. Interconnection Request R1003 (Gas+Other) | Gas | TX | 6.1 yrs | 1,166 MW | Interconnection study | — |
| Interconnection Request 22INR0400 (Solar+Battery) | Solar | TX | 6.0 yrs | 408 MW | Interconnection study | Facility Study |
| Interconnection Request 22INR0402 (Solar+Battery) | Solar | TX | 6.0 yrs | 504 MW | Interconnection study | Facility Study |
| Interconnection Request 23INR0055 (Solar) | Solar | TX | 6.0 yrs | 506 MW | Interconnection study | Facility Study |
| Interconnection Request 22INR0350 (Solar) | Solar | TX | 6.0 yrs | 287 MW | Interconnection study | Facility Study |
| Interconnection Request 22INR0423 (Battery) | Storage | TX | 5.9 yrs | 301 MW | Interconnection study | Facility Study |
| Interconnection Request 22INR0462 (Solar+Battery) | Solar | TX | 5.8 yrs | 512 MW | Interconnection study | Facility Study |
| Interconnection Request 23INR0139 (Battery) | Storage | TX | 5.8 yrs | 302 MW | Interconnection study | Facility Study |
| Interconnection Request 24INR0011 (Solar+Battery) | Solar | TX | 5.8 yrs | 503 MW | Interconnection study | Facility Study |
| Interconnection Request 22INR0480 (Wind) | Wind (onshore) | TX | 5.6 yrs | 300 MW | Interconnection study | Facility Study |
| Interconnection Request 23INR0209 (Solar+Battery) | Solar | TX | 5.5 yrs | 508 MW | Interconnection study | Facility Study |
| Interconnection Request 23INR0214 (Solar+Battery) | Solar | TX | 5.5 yrs | 503 MW | Interconnection study | Facility Study |
| Interconnection Request 22INR0497 (Gas) | Gas | TX | 5.5 yrs | 680 MW | Interconnection study | Facility Study |
| Interconnection Request 23INR0227 (Solar+Battery) | Solar | TX | 5.4 yrs | 255 MW | Interconnection study | Facility Study |
| Interconnection Request 23INR0228 (Solar+Battery) | Solar | TX | 5.4 yrs | 604 MW | Interconnection study | Facility Study |
| SPS Interconnection Request GEN-2021-090 (Solar+Battery) | Solar | TX | 5.4 yrs | 400 MW | Interconnection study | Facility Study |
| Interconnection Request 23INR0127 (Battery) | Storage | TX | 5.3 yrs | 409 MW | Interconnection study | Facility Study |
| Interconnection Request 23INR0126 (Battery) | Storage | TX | 5.3 yrs | 408 MW | Interconnection study | Facility Study |
| Interconnection Request 23INR0272 (Battery) | Storage | TX | 5.3 yrs | 304 MW | Interconnection study | Facility Study |
| Interconnection Request 24INR0118 (Solar+Battery) | Solar | TX | 5.0 yrs | 262 MW | Interconnection study | Facility Study |
| Interconnection Request 23INR0273 (Solar) | Solar | TX | 5.0 yrs | 439 MW | Interconnection study | Facility Study |
| Interconnection Request 23INR0330 (Battery) | Storage | TX | 5.0 yrs | 411 MW | Interconnection study | Facility Study |
| Interconnection Request 24INR0094 (Solar+Battery) | Solar | TX | 5.0 yrs | 666 MW | Interconnection study | Facility Study |
| Interconnection Request 24INR0125 (Solar) | Solar | TX | 4.9 yrs | 408 MW | Interconnection study | Facility Study |
| Interconnection Request 24INR0098 (Solar+Battery) | Solar | TX | 4.9 yrs | 509 MW | Interconnection study | Facility Study |
| Interconnection Request 24INR0095 (Solar+Battery) | Solar | TX | 4.9 yrs | 666 MW | Interconnection study | Facility Study |
| Interconnection Request 24INR0145 (Gas) | Gas | TX | 4.8 yrs | 450 MW | Interconnection study | Facility Study |
| Interconnection Request 24INR0097 (Solar+Battery) | Solar | TX | 4.7 yrs | 666 MW | Interconnection study | Facility Study |
| Interconnection Request 24INR0130 (Battery) | Storage | TX | 4.7 yrs | 411 MW | Interconnection study | Facility Study |
| Interconnection Request 24INR0135 (Battery) | Storage | TX | 4.7 yrs | 410 MW | Interconnection study | Facility Study |
| Interconnection Request 24INR0157 (Battery) | Storage | TX | 4.7 yrs | 402 MW | Interconnection study | Facility Study |
| Interconnection Request 24INR0172 (Solar+Battery) | Solar | TX | 4.6 yrs | 402 MW | Interconnection study | Facility Study |
| Interconnection Request 23INR0233 (Solar) | Solar | TX | 4.5 yrs | 371 MW | Interconnection study | Facility Study |
| Interconnection Request 24INR0282 (Battery) | Storage | TX | 4.4 yrs | 311 MW | Interconnection study | Facility Study |
| Interconnection Request 25INR0057 (Solar) | Solar | TX | 4.4 yrs | 352 MW | Interconnection study | Facility Study |
| Interconnection Request 24INR0368 (Solar+Battery) | Solar | TX | 4.2 yrs | 305 MW | Interconnection study | Facility Study |
| Interconnection Request 24INR0404 (Solar+Battery) | Solar | TX | 4.1 yrs | 508 MW | Interconnection study | Facility Study |
| Interconnection Request 30INR0002 (Other) | Other | TX | 4.1 yrs | 1,232 MW | Interconnection study | Facility Study |
| Interconnection Request 24INR0413 (Battery) | Storage | TX | 4.0 yrs | 304 MW | Interconnection study | Facility Study |
| Interconnection Request 24INR0423 (Solar+Battery) | Solar | TX | 4.0 yrs | 460 MW | Interconnection study | Facility Study |
| Interconnection Request 25INR0176 (Battery) | Storage | TX | 4.0 yrs | 257 MW | Interconnection study | Facility Study |
| ENTERGY TEXAS, INC. Interconnection Request J3045 (Solar) | Solar | TX | 4.0 yrs | 300 MW | Interconnection study | Cluster Study |
| Interconnection Request 25INR0195 (Solar+Battery) | Solar | TX | 4.0 yrs | 300 MW | Interconnection study | Facility Study |
| Interconnection Request 25INR0207 (Solar) | Solar | TX | 3.9 yrs | 808 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0019 (Solar) | Solar | TX | 3.9 yrs | 347 MW | Interconnection study | Facility Study |
| Interconnection Request 24INR0412 (Solar+Battery) | Solar | TX | 3.9 yrs | 296 MW | Interconnection study | Facility Study |
| Interconnection Request 25INR0177 (Wind) | Wind (onshore) | TX | 3.9 yrs | 302 MW | Interconnection study | Facility Study |
| Interconnection Request 24INR0420 (Solar+Battery) | Solar | TX | 3.9 yrs | 298 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0028 (Solar) | Solar | TX | 3.9 yrs | 302 MW | Interconnection study | Facility Study |
| Interconnection Request 25INR0152 (Solar+Battery) | Solar | TX | 3.8 yrs | 402 MW | Interconnection study | Facility Study |
| Interconnection Request 24INR0444 (Solar+Battery) | Solar | TX | 3.8 yrs | 504 MW | Interconnection study | Facility Study |
| Interconnection Request 25INR0288 (Solar+Battery) | Solar | TX | 3.7 yrs | 308 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0045 (Battery) | Storage | TX | 3.6 yrs | 408 MW | Interconnection study | Facility Study |
| Interconnection Request 25INR0339 (Battery) | Storage | TX | 3.6 yrs | 251 MW | Interconnection study | Facility Study |
| Interconnection Request 24INR0500 (Battery) | Storage | TX | 3.6 yrs | 406 MW | Interconnection study | Facility Study |
| Interconnection Request 25INR0196 (Solar+Battery) | Solar | TX | 3.5 yrs | 281 MW | Interconnection study | Facility Study |
| Interconnection Request 25INR0197 (Solar+Battery) | Solar | TX | 3.5 yrs | 287 MW | Interconnection study | Facility Study |
| AEP Interconnection Request GEN-2022-139 (Battery) | Storage | TX | 3.5 yrs | 300 MW | Interconnection study | Facility Study |
| Interconnection Request 25INR0331 (Solar+Battery) | Solar | TX | 3.5 yrs | 251 MW | Interconnection study | Facility Study |
| Interconnection Request 25INR0297 (Solar+Battery) | Solar | TX | 3.5 yrs | 302 MW | Interconnection study | Facility Study |
| Interconnection Request 24INR0508 (Wind) | Wind (onshore) | TX | 3.5 yrs | 607 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0020 (Solar+Battery) | Solar | TX | 3.4 yrs | 364 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0089 (Battery) | Storage | TX | 3.4 yrs | 508 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0110 (Solar+Battery) | Solar | TX | 3.4 yrs | 410 MW | Interconnection study | Facility Study |
| Interconnection Request 25INR0417 (Battery) | Storage | TX | 3.4 yrs | 251 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0114 (Battery) | Storage | TX | 3.4 yrs | 260 MW | Interconnection study | Facility Study |
| Interconnection Request 25INR0238 (Battery) | Storage | TX | 3.3 yrs | 252 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0082 (Solar+Battery) | Solar | TX | 3.3 yrs | 302 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0008 (Solar+Battery) | Solar | TX | 3.3 yrs | 504 MW | Interconnection study | Facility Study |
| Interconnection Request 25INR0451 (Solar+Battery) | Solar | TX | 3.3 yrs | 290 MW | Interconnection study | Facility Study |
| Interconnection Request 24INR0567 (Gas) | Gas | TX | 3.3 yrs | 306 MW | Interconnection study | Facility Study |
| Interconnection Request 25INR0301 (Battery) | Storage | TX | 3.3 yrs | 257 MW | Interconnection study | Facility Study |
| Interconnection Request 25INR0434 (Battery) | Storage | TX | 3.2 yrs | 251 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0143 (Solar) | Solar | TX | 3.2 yrs | 265 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0107 (Battery) | Storage | TX | 3.2 yrs | 502 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0183 (Gas) | Gas | TX | 3.2 yrs | 453 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0061 (Wind) | Wind (onshore) | TX | 3.2 yrs | 1,542 MW | Interconnection study | Facility Study |
| Interconnection Request 30INR0003 (Wind) | Wind (onshore) | TX | 3.2 yrs | 1,029 MW | Interconnection study | Facility Study |
| Interconnection Request 30INR0004 (Wind) | Wind (onshore) | TX | 3.2 yrs | 1,029 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0005 (Solar) | Solar | TX | 3.1 yrs | 359 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0171 (Solar) | Solar | TX | 3.0 yrs | 252 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0172 (Solar) | Solar | TX | 3.0 yrs | 252 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0174 (Battery) | Storage | TX | 3.0 yrs | 252 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0173 (Battery) | Storage | TX | 3.0 yrs | 252 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0086 (Solar+Battery) | Solar | TX | 3.0 yrs | 614 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0077 (Solar+Battery) | Solar | TX | 2.9 yrs | 307 MW | Interconnection study | Facility Study |
| AEP Interconnection Request GEN-2023-204 (Gas) | Gas | TX | 2.9 yrs | 915 MW | Interconnection study | Facility Study |
| Interconnection Request 23INR0368 (Solar) | Solar | TX | 2.9 yrs | 602 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0087 (Solar+Battery) | Solar | TX | 2.9 yrs | 507 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0230 (Solar) | Solar | TX | 2.9 yrs | 502 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0211 (Solar) | Solar | TX | 2.9 yrs | 338 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0277 (Solar+Battery) | Solar | TX | 2.9 yrs | 453 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0294 (Gas) | Gas | TX | 2.9 yrs | 600 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0351 (Gas) | Gas | TX | 2.8 yrs | 660 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0095 (Gas) | Gas | TX | 2.8 yrs | 311 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0096 (Battery) | Storage | TX | 2.8 yrs | 301 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0082 (Battery) | Storage | TX | 2.8 yrs | 502 MW | Interconnection study | Facility Study |
| Interconnection Request 24INR0576 (Gas) | Gas | TX | 2.8 yrs | 400 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0091 (Battery) | Storage | TX | 2.8 yrs | 310 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0023 (Solar) | Solar | TX | 2.8 yrs | 410 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0009 (Solar) | Solar | TX | 2.8 yrs | 445 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0010 (Wind) | Wind (onshore) | TX | 2.8 yrs | 622 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0011 (Solar) | Solar | TX | 2.8 yrs | 445 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0012 (Wind) | Wind (onshore) | TX | 2.8 yrs | 623 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0300 (Solar) | Solar | TX | 2.7 yrs | 302 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0306 (Battery) | Storage | TX | 2.7 yrs | 256 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0143 (Battery) | Storage | TX | 2.7 yrs | 252 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0108 (Wind) | Wind (onshore) | TX | 2.7 yrs | 379 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0140 (Wind) | Wind (onshore) | TX | 2.7 yrs | 606 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0142 (Battery) | Storage | TX | 2.7 yrs | 279 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0030 (Battery) | Storage | TX | 2.7 yrs | 251 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0043 (Solar) | Solar | TX | 2.7 yrs | 503 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0334 (Battery) | Storage | TX | 2.6 yrs | 523 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0311 (Solar+Battery) | Solar | TX | 2.6 yrs | 251 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0149 (Battery) | Storage | TX | 2.6 yrs | 314 MW | Interconnection study | Facility Study |
| RAYBURN COUNTRY ELECTRIC COOPERATIVE, INC (TX PUCT Docket 56234) | Transmission | TX | 2.5 yrs | Not disclosed | Local/state review | — |
| Interconnection Request 27INR0218 (Solar) | Solar | TX | 2.5 yrs | 301 MW | Interconnection study | Facility Study |
| Interconnection Request 25INR0582 (Battery) | Storage | TX | 2.5 yrs | 256 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0190 (Battery) | Storage | TX | 2.5 yrs | 502 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0115 (Battery) | Storage | TX | 2.5 yrs | 514 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0195 (Battery) | Storage | TX | 2.5 yrs | 401 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0040 (Solar) | Solar | TX | 2.5 yrs | 251 MW | Interconnection study | Facility Study |
| Interconnection Request 25INR0588 (Solar+Battery) | Solar | TX | 2.5 yrs | 805 MW | Interconnection study | Facility Study |
| Interconnection Request 25INR0608 (Solar+Battery) | Solar | TX | 2.5 yrs | 600 MW | Interconnection study | Facility Study |
| Interconnection Request 25INR0587 (Solar+Battery) | Solar | TX | 2.5 yrs | 1,043 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0370 (Gas) | Gas | TX | 2.5 yrs | 750 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0425 (Solar) | Solar | TX | 2.5 yrs | 358 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0422 (Battery) | Storage | TX | 2.5 yrs | 255 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0071 (Gas) | Gas | TX | 2.5 yrs | 1,292 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0141 (Solar) | Solar | TX | 2.5 yrs | 403 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0192 (Solar+Battery) | Solar | TX | 2.5 yrs | 451 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0221 (Solar+Battery) | Solar | TX | 2.5 yrs | 896 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0222 (Solar+Battery) | Solar | TX | 2.5 yrs | 284 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0207 (Battery) | Storage | TX | 2.5 yrs | 304 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0017 (Wind) | Wind (onshore) | TX | 2.5 yrs | 600 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0063 (Solar) | Solar | TX | 2.5 yrs | 402 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0059 (Solar) | Solar | TX | 2.5 yrs | 261 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0386 (Wind+Battery) | Wind (onshore) | TX | 2.4 yrs | 987 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0387 (Wind+Battery) | Wind (onshore) | TX | 2.4 yrs | 446 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0057 (Wind) | Wind (onshore) | TX | 2.4 yrs | 420 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0188 (Solar+Battery) | Solar | TX | 2.4 yrs | 411 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0132 (Wind+Battery) | Wind (onshore) | TX | 2.4 yrs | 298 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0061 (Solar+Battery) | Solar | TX | 2.4 yrs | 310 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0235 (Battery) | Storage | TX | 2.4 yrs | 517 MW | Interconnection study | Facility Study |
| Interconnection Request 25INR0660 (Battery) | Storage | TX | 2.3 yrs | 306 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0075 (Battery) | Storage | TX | 2.3 yrs | 313 MW | Interconnection study | Facility Study |
| Interconnection Request 25INR0632 (Solar) | Solar | TX | 2.3 yrs | 576 MW | Interconnection study | Facility Study |
| Interconnection Request 25INR0589 (Solar+Battery) | Solar | TX | 2.3 yrs | 1,043 MW | Interconnection study | Facility Study |
| Interconnection Request 25INR0586 (Solar+Battery) | Solar | TX | 2.3 yrs | 504 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0086 (Solar+Battery) | Solar | TX | 2.3 yrs | 403 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0252 (Battery) | Storage | TX | 2.3 yrs | 251 MW | Interconnection study | Facility Study |
| Interconnection Request 25INR0656 (Battery) | Storage | TX | 2.3 yrs | 306 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0186 (Solar+Battery) | Solar | TX | 2.3 yrs | 302 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0026 (Solar) | Solar | TX | 2.3 yrs | 251 MW | Interconnection study | Facility Study |
| LONE STAR TRANSMISSION, LLC (TX PUCT Docket 56599) | Transmission | TX | 2.2 yrs | Not disclosed | Local/state review | — |
| Interconnection Request 24INR0763 (Battery) | Storage | TX | 2.2 yrs | 307 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0503 (Battery) | Storage | TX | 2.2 yrs | 256 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0086 (Gas) | Gas | TX | 2.2 yrs | 888 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0087 (Gas) | Gas | TX | 2.2 yrs | 479 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0090 (Gas) | Gas | TX | 2.2 yrs | 1,036 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0013 (Solar) | Solar | TX | 2.2 yrs | 307 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0309 (Solar) | Solar | TX | 2.2 yrs | 252 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0310 (Wind) | Wind (onshore) | TX | 2.2 yrs | 523 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0088 (Solar+Battery) | Solar | TX | 2.2 yrs | 309 MW | Interconnection study | Facility Study |
| Interconnection Request 25INR0653 (Battery) | Storage | TX | 2.1 yrs | 306 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0527 (Solar+Battery) | Solar | TX | 2.1 yrs | 300 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0084 (Gas) | Gas | TX | 2.1 yrs | 1,536 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0111 (Solar+Battery) | Solar | TX | 2.1 yrs | 400 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0031 (Wind) | Wind (onshore) | TX | 2.1 yrs | 641 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0030 (Solar) | Solar | TX | 2.1 yrs | 502 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0034 (Solar) | Solar | TX | 2.1 yrs | 502 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0035 (Wind) | Wind (onshore) | TX | 2.1 yrs | 641 MW | Interconnection study | Facility Study |
| ENTERGY TEXAS, INC. (TX PUCT Docket 56865) | Other | TX | 2.1 yrs | Not disclosed | Local/state review | — |
| Interconnection Request 29INR0041 (Gas) | Gas | TX | 2.1 yrs | 260 MW | Interconnection study | Facility Study |
| LYNTEGAR ELECTRIC COOPERATIVE, INC (TX PUCT Docket 56950) | Transmission | TX | 2.1 yrs | Not disclosed | Local/state review | — |
| Interconnection Request 26INR0545 (Battery) | Storage | TX | 2.1 yrs | 522 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0550 (Battery) | Storage | TX | 2.1 yrs | 253 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0216 (Battery) | Storage | TX | 2.1 yrs | 256 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0291 (Battery) | Storage | TX | 2.1 yrs | 256 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0072 (Wind) | Wind (onshore) | TX | 2.1 yrs | 479 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0019 (Solar) | Solar | TX | 2.1 yrs | 402 MW | Interconnection study | Facility Study |
| Arkansas Electric Cooperative Corporation (AR PSC Docket 24-045-U) | Gas | TX | 2.1 yrs | Not disclosed | Local/state review | — |
| DOS AGUAS, LLC (TX PUCT Docket 56971) | Other | TX | 2.0 yrs | Not disclosed | Local/state review | — |
| Interconnection Request 26INR0546 (Battery) | Storage | TX | 2.0 yrs | 603 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0294 (Battery) | Storage | TX | 2.0 yrs | 403 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0097 (Battery) | Storage | TX | 2.0 yrs | 515 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0132 (Solar+Battery) | Solar | TX | 2.0 yrs | 502 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0157 (Battery) | Storage | TX | 1.9 yrs | 307 MW | Interconnection study | Facility Study |
| SPS Interconnection Request GEN-2024-015 (Solar+Battery) | Solar | TX | 1.9 yrs | 280 MW | Interconnection study | System Impact Study |
| Interconnection Request 28INR0179 (Solar+Battery) | Solar | TX | 1.9 yrs | 302 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0181 (Solar+Battery) | Solar | TX | 1.9 yrs | 256 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0056 (Solar+Battery) | Solar | TX | 1.9 yrs | 301 MW | Interconnection study | Facility Study |
| Interconnection Request J3986 (Solar) | Solar | TX | 1.9 yrs | 270 MW | Interconnection study | — |
| Interconnection Request 28INR0067 (Solar) | Solar | TX | 1.9 yrs | 800 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0169 (Wind) | Wind (onshore) | TX | 1.9 yrs | 293 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0198 (Solar+Battery) | Solar | TX | 1.9 yrs | 302 MW | Interconnection study | Facility Study |
| AEP Interconnection Request GEN-2024-025 (Solar) | Solar | TX | 1.9 yrs | 300 MW | Interconnection study | System Impact Study |
| SPS Interconnection Request GEN-2024-041 (Wind) | Wind (onshore) | TX | 1.9 yrs | 250 MW | Interconnection study | System Impact Study |
| SPS Interconnection Request GEN-2024-045 (Solar) | Solar | TX | 1.9 yrs | 345 MW | Interconnection study | System Impact Study |
| SPS Interconnection Request GEN-2024-046 (Solar) | Solar | TX | 1.9 yrs | 345 MW | Interconnection study | System Impact Study |
| SPS Interconnection Request GEN-2024-050 (Solar+Battery) | Solar | TX | 1.9 yrs | 300 MW | Interconnection study | System Impact Study |
| SPS Interconnection Request GEN-2024-063 (Solar) | Solar | TX | 1.9 yrs | 256 MW | Interconnection study | System Impact Study |
| SPS Interconnection Request GEN-2024-042 (Wind) | Wind (onshore) | TX | 1.9 yrs | 250 MW | Interconnection study | System Impact Study |
| AEP Interconnection Request GEN-2024-068 (Solar) | Solar | TX | 1.9 yrs | 300 MW | Interconnection study | System Impact Study |
| SPS Interconnection Request GEN-2024-077 (Solar) | Solar | TX | 1.9 yrs | 300 MW | Interconnection study | System Impact Study |
| SPS Interconnection Request GEN-2024-078 (Solar) | Solar | TX | 1.9 yrs | 300 MW | Interconnection study | System Impact Study |
| CITY OF SAN ANTONIO, ACTING BY AND THROUGH THE CITY PUBLIC SERVICE BOARD (CPS ENERGY) (TX PUCT Docket 57206) | Transmission | TX | 1.8 yrs | Not disclosed | Local/state review | — |
| Interconnection Request 26INR0525 (Battery) | Storage | TX | 1.8 yrs | 416 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0615 (Battery) | Storage | TX | 1.8 yrs | 256 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0386 (Solar+Battery) | Solar | TX | 1.8 yrs | 306 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0113 (Wind) | Wind (onshore) | TX | 1.8 yrs | 750 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0118 (Battery) | Storage | TX | 1.8 yrs | 307 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0194 (Solar+Battery) | Solar | TX | 1.8 yrs | 302 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0025 (Wind) | Wind (onshore) | TX | 1.8 yrs | 370 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0068 (Gas) | Gas | TX | 1.8 yrs | 470 MW | Interconnection study | Facility Study |
| AEP TEXAS INC. (TX PUCT Docket 57245) | Transmission | TX | 1.8 yrs | Not disclosed | Local/state review | — |
| Interconnection Request 27INR0385 (Solar+Battery) | Solar | TX | 1.8 yrs | 252 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0186 (Battery) | Storage | TX | 1.8 yrs | 257 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0365 (Battery) | Storage | TX | 1.8 yrs | 614 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0609 (Solar) | Solar | TX | 1.7 yrs | 600 MW | Interconnection study | Facility Study |
| SOUTHWESTERN ELECTRIC POWER COMPANY (TX PUCT Docket 57376) | Gas | TX | 1.7 yrs | Not disclosed | Local/state review | — |
| Interconnection Request 26INR0465 (Battery) | Storage | TX | 1.7 yrs | 606 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0119 (Battery) | Storage | TX | 1.7 yrs | 342 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0223 (Solar) | Solar | TX | 1.7 yrs | 255 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0245 (Solar+Battery) | Solar | TX | 1.7 yrs | 403 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0242 (Wind) | Wind (onshore) | TX | 1.7 yrs | 302 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0082 (Solar) | Solar | TX | 1.7 yrs | 300 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0612 (Battery) | Storage | TX | 1.7 yrs | 308 MW | Interconnection study | Facility Study |
| EL PASO ELECTRIC COMPANY (TX PUCT Docket 57501) | Solar | TX | 1.7 yrs | 100 MW | Local/state review | — |
| Interconnection Request 27INR0367 (Wind+Battery) | Wind (onshore) | TX | 1.6 yrs | 303 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0108 (Gas) | Gas | TX | 1.6 yrs | 570 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0270 (Solar+Battery) | Solar | TX | 1.6 yrs | 302 MW | Interconnection study | Facility Study |
| Interconnection Request 30INR0018 (Wind) | Wind (onshore) | TX | 1.6 yrs | 1,500 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0630 (Battery) | Storage | TX | 1.6 yrs | 500 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0633 (Battery) | Storage | TX | 1.6 yrs | 500 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0447 (Battery) | Storage | TX | 1.6 yrs | 259 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0452 (Solar+Battery) | Solar | TX | 1.6 yrs | 603 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0180 (Solar+Battery) | Solar | TX | 1.6 yrs | 357 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0185 (Solar+Battery) | Solar | TX | 1.6 yrs | 255 MW | Interconnection study | Facility Study |
| Interconnection Request 30INR0031 (Gas) | Gas | TX | 1.6 yrs | 1,500 MW | Interconnection study | Facility Study |
| ENTERGY TEXAS, INC. Interconnection Request J3902 (Wind) | Wind (onshore) | TX | 1.6 yrs | 289 MW | Interconnection study | — |
| Interconnection Request 27INR0438 (Solar+Battery) | Solar | TX | 1.6 yrs | 299 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0212 (Solar+Battery) | Solar | TX | 1.6 yrs | 302 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0466 (Battery) | Storage | TX | 1.6 yrs | 612 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0392 (Battery) | Storage | TX | 1.6 yrs | 301 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0445 (Wind) | Wind (onshore) | TX | 1.6 yrs | 379 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0277 (Battery) | Storage | TX | 1.6 yrs | 306 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0278 (Battery) | Storage | TX | 1.5 yrs | 306 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0063 (Wind) | Wind (onshore) | TX | 1.5 yrs | 295 MW | Interconnection study | Facility Study |
| BROWNSVILLE PUBLIC UTILITIES BOARD (TX PUCT Docket 57750) | Other | TX | 1.5 yrs | Not disclosed | Local/state review | — |
| TEXAS WATER UTILITIES, L.P. (TX PUCT Docket 57776) | Other | TX | 1.5 yrs | Not disclosed | Local/state review | — |
| SPS Interconnection Request GEN-2024-109 (Wind) | Wind (onshore) | TX | 1.5 yrs | 401 MW | Interconnection study | System Impact Study |
| SPS Interconnection Request GEN-2024-099 (Solar) | Solar | TX | 1.5 yrs | 300 MW | Interconnection study | System Impact Study |
| SPS Interconnection Request GEN-2024-145 (Wind) | Wind (onshore) | TX | 1.5 yrs | 250 MW | Interconnection study | System Impact Study |
| SPS Interconnection Request GEN-2024-143 (Wind) | Wind (onshore) | TX | 1.5 yrs | 250 MW | Interconnection study | System Impact Study |
| SPS Interconnection Request GEN-2024-153 (Solar) | Solar | TX | 1.5 yrs | 250 MW | Interconnection study | System Impact Study |
| AEP Interconnection Request GEN-2024-230 (Battery) | Storage | TX | 1.5 yrs | 300 MW | Interconnection study | System Impact Study |
| AEP Interconnection Request GEN-2024-232 (Solar) | Solar | TX | 1.5 yrs | 250 MW | Interconnection study | System Impact Study |
| SPS Interconnection Request GEN-2024-280 (Solar+Battery) | Solar | TX | 1.5 yrs | 350 MW | Interconnection study | System Impact Study |
| SPS Interconnection Request GEN-2024-317 (Solar) | Solar | TX | 1.5 yrs | 300 MW | Interconnection study | System Impact Study |
| SPS Interconnection Request GEN-2024-266 (Solar+Battery) | Solar | TX | 1.5 yrs | 500 MW | Interconnection study | System Impact Study |
| SPS Interconnection Request GEN-2024-336 (Solar+Battery) | Solar | TX | 1.5 yrs | 300 MW | Interconnection study | System Impact Study |
| SPS Interconnection Request GEN-2024-364 (Solar+Battery) | Solar | TX | 1.5 yrs | 300 MW | Interconnection study | System Impact Study |
| SPS Interconnection Request GEN-2024-368 (Battery) | Storage | TX | 1.5 yrs | 250 MW | Interconnection study | System Impact Study |
| AEP Interconnection Request GEN-2024-343 (Gas) | Gas | TX | 1.5 yrs | 471 MW | Interconnection study | System Impact Study |
| AEP Interconnection Request GEN-2024-377 (Gas) | Gas | TX | 1.5 yrs | 1,350 MW | Interconnection study | System Impact Study |
| Interconnection Request 28INR0250 (Solar+Battery) | Solar | TX | 1.5 yrs | 528 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0033 (Wind) | Wind (onshore) | TX | 1.5 yrs | 641 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0032 (Solar) | Solar | TX | 1.5 yrs | 502 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0605 (Battery) | Storage | TX | 1.5 yrs | 314 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0443 (Wind) | Wind (onshore) | TX | 1.5 yrs | 473 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0280 (Wind) | Wind (onshore) | TX | 1.5 yrs | 303 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0332 (Solar+Battery) | Solar | TX | 1.5 yrs | 601 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0120 (Gas) | Gas | TX | 1.5 yrs | 846 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0603 (Solar+Battery) | Solar | TX | 1.4 yrs | 306 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0166 (Battery) | Storage | TX | 1.4 yrs | 351 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0335 (Solar) | Solar | TX | 1.4 yrs | 251 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0327 (Battery) | Storage | TX | 1.4 yrs | 407 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0125 (Solar+Battery) | Solar | TX | 1.4 yrs | 301 MW | Interconnection study | Facility Study |
| CITY OF SAN ANTONIO, ACTING BY AND THROUGH THE CITY PUBLIC SERVICE BOARD (CPS ENERGY) (TX PUCT Docket 57849) | Other | TX | 1.4 yrs | Not disclosed | Local/state review | — |
| LONE STAR TRANSMISSION, LLC (TX PUCT Docket 57836) | Other | TX | 1.4 yrs | Not disclosed | Local/state review | — |
| Interconnection Request 26INR0664 (Gas) | Gas | TX | 1.4 yrs | 655 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0647 (Wind) | Wind (onshore) | TX | 1.4 yrs | 251 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0150 (Solar+Battery) | Solar | TX | 1.4 yrs | 503 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0451 (Battery) | Storage | TX | 1.4 yrs | 302 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0492 (Solar+Battery) | Solar | TX | 1.4 yrs | 301 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0497 (Gas) | Gas | TX | 1.4 yrs | 495 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0499 (Solar) | Solar | TX | 1.4 yrs | 500 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0285 (Battery) | Storage | TX | 1.4 yrs | 410 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0328 (Battery) | Storage | TX | 1.4 yrs | 307 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0122 (Solar) | Solar | TX | 1.4 yrs | 301 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0115 (Solar+Battery) | Solar | TX | 1.4 yrs | 311 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0147 (Solar) | Solar | TX | 1.4 yrs | 300 MW | Interconnection study | Facility Study |
| ENTERGY TEXAS, INC. (TX PUCT Docket 58005) | Transmission | TX | 1.4 yrs | Not disclosed | Local/state review | — |
| Interconnection Request 27INR0474 (Wind) | Wind (onshore) | TX | 1.4 yrs | 282 MW | Interconnection study | Facility Study |
| ONCOR ELECTRIC DELIVERY COMPANY LLC (TX PUCT Docket 58007) | Transmission | TX | 1.3 yrs | Not disclosed | Local/state review | — |
| BROWNSVILLE PUBLIC UTILITIES BOARD (TX PUCT Docket 58125) | Other | TX | 1.3 yrs | Not disclosed | Local/state review | — |
| ONCOR ELECTRIC DELIVERY COMPANY LLC (TX PUCT Docket 58050) | Transmission | TX | 1.3 yrs | Not disclosed | Local/state review | — |
| AEP TEXAS INC. (TX PUCT Docket 58015) | Transmission | TX | 1.3 yrs | Not disclosed | Local/state review | — |
| Interconnection Request 26INR0560 (Gas) | Gas | TX | 1.3 yrs | 506 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0493 (Solar+Battery) | Solar | TX | 1.3 yrs | 261 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0322 (Solar+Battery) | Solar | TX | 1.3 yrs | 252 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0323 (Solar+Battery) | Solar | TX | 1.3 yrs | 261 MW | Interconnection study | Facility Study |
| ONCOR ELECTRIC DELIVERY COMPANY LLC (TX PUCT Docket 58126) | Transmission | TX | 1.3 yrs | Not disclosed | Local/state review | — |
| Interconnection Request 27INR0529 (Solar+Battery) | Solar | TX | 1.3 yrs | 504 MW | Interconnection study | Facility Study |
| El Paso Electric Company Interconnection Request Q25-LG-6-5 (Battery) | Storage | TX | 1.3 yrs | 250 MW | Interconnection study | In Progress (unknown study) |
| Interconnection Request 27INR0535 (Solar+Battery) | Solar | TX | 1.3 yrs | 1,043 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0205 (Solar+Battery) | Solar | TX | 1.3 yrs | 503 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0215 (Wind) | Wind (onshore) | TX | 1.3 yrs | 971 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0288 (Battery) | Storage | TX | 1.3 yrs | 302 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0307 (Wind) | Wind (onshore) | TX | 1.3 yrs | 303 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0292 (Battery) | Storage | TX | 1.3 yrs | 359 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0103 (Wind) | Wind (onshore) | TX | 1.3 yrs | 709 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0119 (Battery) | Storage | TX | 1.2 yrs | 302 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0148 (Solar) | Solar | TX | 1.2 yrs | 506 MW | Interconnection study | Facility Study |
| DENTON COUNTY ELECTRIC COOPERATIVE, INC. (TX PUCT Docket 58257) | Other | TX | 1.2 yrs | Not disclosed | Local/state review | — |
| Interconnection Request 26INR0686 (Solar+Battery) | Solar | TX | 1.2 yrs | 1,043 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0409 (Battery) | Storage | TX | 1.2 yrs | 287 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0488 (Solar) | Solar | TX | 1.2 yrs | 302 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0260 (Solar+Battery) | Solar | TX | 1.2 yrs | 554 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0281 (Solar) | Solar | TX | 1.2 yrs | 281 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0385 (Solar) | Solar | TX | 1.2 yrs | 302 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0151 (Battery) | Storage | TX | 1.2 yrs | 304 MW | Interconnection study | Facility Study |
| Interconnection Request 30INR0051 (Gas) | Gas | TX | 1.2 yrs | 880 MW | Interconnection study | Facility Study |
| Interconnection Request 30INR0052 (Gas) | Gas | TX | 1.2 yrs | 880 MW | Interconnection study | Facility Study |
| ENTERGY TEXAS , INC. (TX PUCT Docket 58324) | Other | TX | 1.2 yrs | Not disclosed | Local/state review | — |
| Interconnection Request 27INR0504 (Solar) | Solar | TX | 1.2 yrs | 503 MW | Interconnection study | Facility Study |
| AEP TEXAS INC. (TX PUCT Docket 58264) | Transmission | TX | 1.2 yrs | Not disclosed | Local/state review | — |
| Interconnection Request 27INR0453 (Solar) | Solar | TX | 1.2 yrs | 273 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0503 (Solar) | Solar | TX | 1.2 yrs | 503 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0536 (Wind) | Wind (onshore) | TX | 1.2 yrs | 493 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0160 (Solar) | Solar | TX | 1.2 yrs | 302 MW | Interconnection study | Facility Study |
| ONCOR ELECTRIC DELIVERY COMPANY LLC (TX PUCT Docket 58344) | Transmission | TX | 1.2 yrs | Not disclosed | Local/state review | — |
| TEXAS-NEW MEXICO POWER COMPANY (TX PUCT Docket 58416) | Other | TX | 1.1 yrs | Not disclosed | Local/state review | — |
| Interconnection Request 29INR0146 (Wind) | Wind (onshore) | TX | 1.1 yrs | 306 MW | Interconnection study | Facility Study |
| Interconnection Request 26INR0685 (Gas) | Gas | TX | 1.1 yrs | 400 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0298 (Solar+Battery) | Solar | TX | 1.1 yrs | 427 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0376 (Wind) | Wind (onshore) | TX | 1.1 yrs | 299 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0375 (Wind) | Wind (onshore) | TX | 1.1 yrs | 301 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0394 (Solar+Battery) | Solar | TX | 1.1 yrs | 282 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0408 (Wind) | Wind (onshore) | TX | 1.1 yrs | 353 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0117 (Wind) | Wind (onshore) | TX | 1.1 yrs | 300 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0173 (Battery) | Storage | TX | 1.1 yrs | 618 MW | Interconnection study | Facility Study |
| Interconnection Request 30INR0054 (Gas) | Gas | TX | 1.1 yrs | 880 MW | Interconnection study | Facility Study |
| Interconnection Request 30INR0053 (Solar) | Solar | TX | 1.1 yrs | 500 MW | Interconnection study | Facility Study |
| Entergy Texas, Inc. Interconnection Request E0030 (Gas) | Gas | TX | 1.1 yrs | 820 MW | Interconnection study | In Progress (unknown study) |
| Entergy Texas, Inc. Interconnection Request E0032 (Gas) | Gas | TX | 1.1 yrs | 478 MW | Interconnection study | In Progress (unknown study) |
| ONCOR ELECTRIC DELIVERY COMPANY LLC (TX PUCT Docket 58453) | Transmission | TX | 1.1 yrs | Not disclosed | Local/state review | — |
| Interconnection Request 28INR0325 (Gas) | Gas | TX | 1.1 yrs | 335 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0351 (Gas) | Gas | TX | 1.1 yrs | 334 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0415 (Wind) | Wind (onshore) | TX | 1.1 yrs | 474 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0353 (Gas) | Gas | TX | 1.1 yrs | 252 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0188 (Solar) | Solar | TX | 1.1 yrs | 415 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0184 (Solar) | Solar | TX | 1.1 yrs | 400 MW | Interconnection study | Facility Study |
| ONCOR ELECTRIC DELIVERY COMPANY LLC (TX PUCT Docket 58562) | Transmission | TX | 1.0 yrs | Not disclosed | Local/state review | — |
| ONCOR ELECTRIC DELIVERY COMPANY LLC (TX PUCT Docket 58561) | Transmission | TX | 1.0 yrs | Not disclosed | Local/state review | — |
| Interconnection Request 27INR0556 (Solar+Battery) | Solar | TX | 1.0 yrs | 301 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0324 (Solar) | Solar | TX | 1.0 yrs | 312 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0171 (Solar+Battery) | Solar | TX | 1.0 yrs | 301 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0172 (Solar+Battery) | Solar | TX | 1.0 yrs | 310 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0175 (Gas) | Gas | TX | 1.0 yrs | 991 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0423 (Solar+Battery) | Solar | TX | 1.0 yrs | 310 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0422 (Solar+Battery) | Solar | TX | 1.0 yrs | 301 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0042 (Wind) | Wind (onshore) | TX | 1.0 yrs | 310 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0169 (Battery) | Storage | TX | 1.0 yrs | 517 MW | Interconnection study | Facility Study |
| Interconnection Request 30INR0058 (Solar) | Solar | TX | 1.0 yrs | 400 MW | Interconnection study | Facility Study |
| ENTERGY TEXAS, INC. (TX PUCT Docket 58662) | Transmission | TX | 1.0 yrs | Not disclosed | Local/state review | — |
| Interconnection Request 28INR0447 (Wind) | Wind (onshore) | TX | 1.0 yrs | 290 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0446 (Wind) | Wind (onshore) | TX | 1.0 yrs | 290 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0183 (Solar) | Solar | TX | 1.0 yrs | 304 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0180 (Gas) | Gas | TX | 1.0 yrs | 1,252 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0181 (Solar) | Solar | TX | 1.0 yrs | 304 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0182 (Solar) | Solar | TX | 1.0 yrs | 304 MW | Interconnection study | Facility Study |
| LONE STAR TRANSMISSION, LLC (TX PUCT Docket 58632) | Transmission | TX | 0.9 yrs | Not disclosed | Local/state review | — |
| LONE STAR TRANSMISSION, LLC (TX PUCT Docket 58764) | Transmission | TX | 0.9 yrs | Not disclosed | Local/state review | — |
| SPS Interconnection Request ERAS-2025-021 (Wind) | Wind (onshore) | TX | 0.9 yrs | 500 MW | Interconnection study | In Progress (unknown study) |
| SPS Interconnection Request ERAS-2025-028 (Solar) | Solar | TX | 0.9 yrs | 384 MW | Interconnection study | In Progress (unknown study) |
| SPS Interconnection Request ERAS-2025-027 (Battery) | Storage | TX | 0.9 yrs | 250 MW | Interconnection study | In Progress (unknown study) |
| Interconnection Request 28INR0434 (Wind) | Wind (onshore) | TX | 0.9 yrs | 367 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0433 (Solar) | Solar | TX | 0.9 yrs | 301 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0167 (Gas) | Gas | TX | 0.9 yrs | 449 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0572 (Gas) | Gas | TX | 0.9 yrs | 371 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0150 (Gas) | Gas | TX | 0.9 yrs | 1,274 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0162 (Gas) | Gas | TX | 0.9 yrs | 1,204 MW | Interconnection study | Facility Study |
| ONCOR ELECTRIC DELIVERY COMPANY LLC (TX PUCT Docket 58879) | Transmission | TX | 0.9 yrs | Not disclosed | Local/state review | — |
| ONCOR ELECTRIC DELIVERY COMPANY LLC (TX PUCT Docket 58848) | Transmission | TX | 0.9 yrs | Not disclosed | Local/state review | — |
| BRAZOS ELECTRIC POWER COOPERATIVE, INC. (BRAZOS ELECTRIC) (TX PUCT Docket 58865) | Transmission | TX | 0.9 yrs | Not disclosed | Local/state review | — |
| Interconnection Request 27INR0334 (Wind) | Wind (onshore) | TX | 0.8 yrs | 740 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0571 (Battery) | Storage | TX | 0.8 yrs | 750 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0582 (Gas) | Gas | TX | 0.8 yrs | 1,238 MW | Interconnection study | Facility Study |
| Interconnection Request 27INR0581 (Gas) | Gas | TX | 0.8 yrs | 1,238 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0114 (Solar) | Solar | TX | 0.8 yrs | 500 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0466 (Battery) | Storage | TX | 0.8 yrs | 750 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0472 (Battery) | Storage | TX | 0.8 yrs | 514 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0473 (Battery) | Storage | TX | 0.8 yrs | 514 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0206 (Gas) | Gas | TX | 0.8 yrs | 942 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0192 (Solar) | Solar | TX | 0.8 yrs | 302 MW | Interconnection study | Facility Study |
| SPS Interconnection Request GEN-2025-GR6 (Wind) | Wind (onshore) | TX | 0.8 yrs | 300 MW | Interconnection study | In Progress (unknown study) |
| Interconnection Request 26INR0635 (Solar) | Solar | TX | 0.8 yrs | 500 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0459 (Gas) | Gas | TX | 0.8 yrs | 950 MW | Interconnection study | Facility Study |
| Interconnection Request 32INR0003 (Gas) | Gas | TX | 0.8 yrs | 1,381 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0217 (Battery) | Storage | TX | 0.8 yrs | 999 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0219 (Solar) | Solar | TX | 0.8 yrs | 301 MW | Interconnection study | Facility Study |
| Interconnection Request 30INR0071 (Gas) | Gas | TX | 0.8 yrs | 1,660 MW | Interconnection study | Facility Study |
| ONCOR ELECTRIC DELIVERY COMPANY LLC (TX PUCT Docket 59044) | Transmission | TX | 0.8 yrs | Not disclosed | Local/state review | — |
| Interconnection Request 28INR0469 (Solar) | Solar | TX | 0.8 yrs | 252 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0470 (Solar) | Solar | TX | 0.8 yrs | 252 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0476 (Solar) | Solar | TX | 0.8 yrs | 276 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0221 (Solar) | Solar | TX | 0.8 yrs | 252 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0220 (Solar) | Solar | TX | 0.8 yrs | 252 MW | Interconnection study | Facility Study |
| EL PASO ELECTRIC COMPANY (TX PUCT Docket 59076) | Gas | TX | 0.7 yrs | 366 MW | Local/state review | — |
| Interconnection Request 30INR0073 (Gas) | Gas | TX | 0.7 yrs | 311 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0390 (Battery) | Storage | TX | 0.7 yrs | 258 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0478 (Wind) | Wind (onshore) | TX | 0.7 yrs | 250 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0204 (Solar+Battery) | Solar | TX | 0.7 yrs | 548 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0203 (Solar+Battery) | Solar | TX | 0.7 yrs | 532 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0196 (Solar) | Solar | TX | 0.7 yrs | 405 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0218 (Battery) | Storage | TX | 0.7 yrs | 1,026 MW | Interconnection study | Facility Study |
| Interconnection Request 28INR0486 (Solar) | Solar | TX | 0.7 yrs | 1,200 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0198 (Solar) | Solar | TX | 0.7 yrs | 509 MW | Interconnection study | Facility Study |
| Interconnection Request 29INR0225 (Solar) | Solar | TX | 0.7 yrs | 306 MW | Interconnection study | Facility Study |
| WIND ENERGY TRANSMISSION TEXAS, LLC (TX PUCT Docket 59183) | Solar | TX | 0.7 yrs | Not disclosed | Local/state review | — |
| ONCOR ELECTRIC DELIVERY COMPANY LLC (TX PUCT Docket 59282) | Transmission | TX | 0.6 yrs | Not disclosed | Local/state review | — |
| ENTERGY TEXAS, INC. (TX PUCT Docket 59292) | Transmission | TX | 0.6 yrs | Not disclosed | Local/state review | — |
| PUC CENTRAL RECORDS (TX PUCT Docket 59297) | Other | TX | 0.6 yrs | Not disclosed | Local/state review | — |
| WIND ENERGY TRANSMISSION TEXAS, LLC (TX PUCT Docket 59199) | Solar | TX | 0.6 yrs | Not disclosed | Local/state review | — |
| ONCOR ELECTRIC DELIVERY COMPANY LLC (TX PUCT Docket 59302) | Transmission | TX | 0.6 yrs | Not disclosed | Local/state review | — |
| ONCOR ELECTRIC DELIVERY COMPANY LLC (TX PUCT Docket 59307) | Transmission | TX | 0.6 yrs | Not disclosed | Local/state review | — |
| ONCOR ELECTRIC DELIVERY COMPANY LLC (TX PUCT Docket 59315) | Transmission | TX | 0.5 yrs | Not disclosed | Local/state review | — |
| ENTERGY TEXAS, INC. (TX PUCT Docket 59430) | Other | TX | 0.5 yrs | Not disclosed | Local/state review | — |
| SAM HOUSTON ELECTRIC COOPERATIVE, INC (TX PUCT Docket 59126) | Transmission | TX | 0.5 yrs | Not disclosed | Local/state review | — |
| SOUTH TEXAS ELECTRIC COOPERATIVE, INC. (TX PUCT Docket 59526) | Transmission | TX | 0.4 yrs | Not disclosed | Local/state review | — |
| EL PASO ELECTRIC COMPANY (TX PUCT Docket 59585) | Storage | TX | 0.4 yrs | 150 MW | Local/state review | — |
| CITY PUBLIC SERVICE BOARD (CPS ENERGY) (TX PUCT Docket 59549) | Transmission | TX | 0.4 yrs | Not disclosed | Local/state review | — |
| EL PASO ELECTRIC COMPANY (TX PUCT Docket 59690) | Solar | TX | 0.4 yrs | Not disclosed | Local/state review | — |
| SOUTHWESTERN PUBLIC SERVICE COMPANY (TX PUCT Docket 59739) | Transmission | TX | 0.3 yrs | Not disclosed | Local/state review | — |
| ONCOR ELECTRIC DELIVERY COMPANY LLC (TX PUCT Docket 59675) | Transmission | TX | 0.3 yrs | Not disclosed | Local/state review | — |
| SOUTHWESTERN PUBLIC SERVICE COMPANY (TX PUCT Docket 59818) | Transmission | TX | 0.3 yrs | Not disclosed | Local/state review | — |
| BRAZOS ELECTRIC POWER COOPERATIVE, INC. (BRAZOS ELECTRIC) (TX PUCT Docket 59782) | Transmission | TX | 0.3 yrs | Not disclosed | Local/state review | — |
| EL PASO ELECTRIC COMPANY (TX PUCT Docket 59836) | Other | TX | 0.3 yrs | Not disclosed | Local/state review | — |
| SOUTHWESTERN PUBLIC SERVICE COMPANY (TX PUCT Docket 59862) | Other | TX | 0.2 yrs | Not disclosed | Local/state review | — |
| EL PASO ELECTRIC COMPANY (TX PUCT Docket 59899) | Transmission | TX | 0.2 yrs | Not disclosed | Local/state review | — |
| AEP TEXAS INC. (TX PUCT Docket 59851) | Transmission | TX | 0.2 yrs | Not disclosed | Local/state review | — |
| ONCOR ELECTRIC DELIVERY COMPANY LLC (TX PUCT Docket 59894) | Transmission | TX | 0.2 yrs | Not disclosed | Local/state review | — |
| BRAZOS ELECTRIC POWER COOPERATIVE, INC. (BRAZOS ELECTRIC) (TX PUCT Docket 59913) | Transmission | TX | 0.2 yrs | Not disclosed | Local/state review | — |
| ONCOR ELECTRIC DELIVERY COMPANY LLC (TX PUCT Docket 59932) | Transmission | TX | 0.1 yrs | Not disclosed | Local/state review | — |
| ONCOR ELECTRIC DELIVERY COMPANY LLC (TX PUCT Docket 60008) | Transmission | TX | 0.1 yrs | Not disclosed | Local/state review | — |
| EL PASO ELECTRIC COMPANY (TX PUCT Docket 60016) | Transmission | TX | 0.1 yrs | Not disclosed | Local/state review | — |
| CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC (TX PUCT Docket 60061) | Other | TX | 0.1 yrs | Not disclosed | Local/state review | — |
| Southwestern Electric Power Company (AR PSC Docket 26-056-U) | Storage | TX | 0.1 yrs | 200 MW | Local/state review | — |
| ONCOR ELECTRIC DELIVERY COMPANY LLC (TX PUCT Docket 59980) | Transmission | TX | 0.1 yrs | Not disclosed | Local/state review | — |
| SOUTHWESTERN PUBLIC SERVICE COMPANY (TX PUCT Docket 60112) | Other | TX | 0.1 yrs | Not disclosed | Local/state review | — |
| ENTERGY TEXAS, INC. (TX PUCT Docket 60130) | Transmission | TX | 0.1 yrs | Not disclosed | Local/state review | — |
| TREX US Red Holly (Unit 701) | Solar | TX | — | 250 MW | Regulatory approvals pending | — |
| Iron Belt (Unit 1) | Storage | TX | — | 400 MW | Planned, approvals not yet initiated | — |
| Hanson (Unit HANSO) | Solar | TX | — | 396 MW | Regulatory approvals pending | — |
| Clairemont Solar (Unit CLAPV) | Solar | TX | — | 250 MW | Planned, approvals not yet initiated | — |
| La Salle ESS (Unit LSBS1) | Storage | TX | — | 500 MW | Planned, approvals not yet initiated | — |
| La Salle Solar (Unit LSPV1) | Solar | TX | — | 500 MW | Planned, approvals not yet initiated | — |
| Lazy U ESS 1 (Unit LUBA1) | Storage | TX | — | 250 MW | Planned, approvals not yet initiated | — |
| Hollow Branch Creek (Unit HB2PV) | Solar | TX | — | 460 MW | Regulatory approvals pending | — |
| Project Matador Gas Plant (PMG) (Unit F1G01) | Gas | TX | — | 260 MW | Planned, approvals not yet initiated | — |
| Project Matador Gas Plant (PMG) (Unit F1G02) | Gas | TX | — | 260 MW | Planned, approvals not yet initiated | — |
| Project Matador Gas Plant (PMG) (Unit F1G03) | Gas | TX | — | 260 MW | Planned, approvals not yet initiated | — |
| Project Matador Gas Plant (PMG) (Unit F2G01) | Gas | TX | — | 260 MW | Planned, approvals not yet initiated | — |
| Project Matador Gas Plant (PMG) (Unit F2G02) | Gas | TX | — | 260 MW | Planned, approvals not yet initiated | — |
| Project Matador Gas Plant (PMG) (Unit F2G03) | Gas | TX | — | 260 MW | Planned, approvals not yet initiated | — |
| Red Hollow Renewable Energy (Unit RDHLW) | Solar | TX | — | 300 MW | Planned, approvals not yet initiated | — |
| Red Hollow Renewable Energy (Unit RHLWB) | Storage | TX | — | 300 MW | Planned, approvals not yet initiated | — |
| Rock N' Roll (Unit RRB) | Storage | TX | — | 250 MW | Regulatory approvals pending | — |
| Elio Energy LLC (Unit ELIBS) | Storage | TX | — | 300 MW | Planned, approvals not yet initiated | — |
| OCI SunRoper (Unit OCIRO) | Solar | TX | — | 260 MW | Regulatory approvals pending | — |
| Uvalde Solar 2 (Unit UVPV2) | Solar | TX | — | 300 MW | Planned, approvals not yet initiated | — |
| Hecate Grid East Valley Storage (Unit RMSY) | Storage | TX | — | 255 MW | Planned, approvals not yet initiated | — |
| Hecate Energy Ramsey Storage (Unit RMSY) | Storage | TX | — | 500 MW | Planned, approvals not yet initiated | — |
| Briggs Solar, LLC (Unit BRIGG) | Solar | TX | — | 305 MW | Regulatory approvals pending | — |
| Sunrose Renewable Energy (Unit SNRSE) | Solar | TX | — | 300 MW | Planned, approvals not yet initiated | — |
| Sunrose Renewable Energy (Unit SRSEB) | Storage | TX | — | 300 MW | Planned, approvals not yet initiated | — |
| Selenite Springs Solar (Unit SSPV) | Solar | TX | — | 250 MW | Regulatory approvals pending | — |
| IP Meitner Wind (Unit MEITW) | Wind (onshore) | TX | — | 500 MW | Regulatory approvals pending | — |
| Changing Winds (Unit CHAN1) | Wind (onshore) | TX | — | 288 MW | Regulatory approvals pending | — |
| Ash Creek BESS (Unit BESS) | Storage | TX | — | 306 MW | Planned, approvals not yet initiated | — |
| Mystic Springs Renewable Energy (Hybrid) (Unit MYSPB) | Storage | TX | — | 250 MW | Planned, approvals not yet initiated | — |
| Mystic Springs Renewable Energy (Hybrid) (Unit MYSPS) | Solar | TX | — | 250 MW | Planned, approvals not yet initiated | — |
| Short Creek Solar (Unit SHRT) | Solar | TX | — | 606 MW | Regulatory approvals pending | — |
| IP Meitner Solar (Unit MEITS) | Solar | TX | — | 500 MW | Regulatory approvals pending | — |
| IP Roman Solar (Unit ROMS) | Solar | TX | — | 500 MW | Regulatory approvals pending | — |
| Legend Power Station (Unit LEG) | Gas | TX | — | 754 MW | Regulatory approvals pending | — |
| Lone Star Power Station (Unit 1A) | Gas | TX | — | 467 MW | Regulatory approvals pending | — |
| Gigawatt Solar (Unit GWT1) | Solar | TX | — | 429 MW | Planned, approvals not yet initiated | — |
| Gigawatt Solar (Unit GWT2) | Solar | TX | — | 344 MW | Planned, approvals not yet initiated | — |
| IP Roman Wind (Unit ROMW) | Wind (onshore) | TX | — | 671 MW | Regulatory approvals pending | — |
| Sunscape Renewable Energy (Unit SNSCB) | Storage | TX | — | 500 MW | Planned, approvals not yet initiated | — |
| Sunscape Renewable Energy (Unit SNSCP) | Solar | TX | — | 500 MW | Planned, approvals not yet initiated | — |
| Sandow Lakes Energy Station (Unit SLES1) | Gas | TX | — | 645 MW | Planned, approvals not yet initiated | — |
| Hecate Energy Harley Hand Solar LLC (Unit 19936) | Solar | TX | — | 514 MW | Planned, approvals not yet initiated | — |
| Soleil (Unit SOLEI) | Solar | TX | — | 450 MW | Regulatory approvals pending | — |
| Cuchillas PV and BESS (Unit GRS2B) | Storage | TX | — | 307 MW | Regulatory approvals pending | — |
| Cuchillas PV and BESS (Unit GRS2P) | Solar | TX | — | 306 MW | Regulatory approvals pending | — |
| Naples Power Plant (Unit 1) | Gas | TX | — | 450 MW | Planned, approvals not yet initiated | — |
| Naples Power Plant (Unit 2) | Gas | TX | — | 450 MW | Planned, approvals not yet initiated | — |
| Sandow Lakes Energy Station (Unit SLES2) | Gas | TX | — | 645 MW | Planned, approvals not yet initiated | — |
| Amerada (Unit AMERA) | Solar | TX | — | 300 MW | Regulatory approvals pending | — |
| Lazy U ESS 2 (Unit LUBA2) | Storage | TX | — | 250 MW | Planned, approvals not yet initiated | — |
| Lazy U Solar 1 (Unit LUPV1) | Solar | TX | — | 250 MW | Planned, approvals not yet initiated | — |
| Lazy U Solar 2 (Unit LUPV2) | Solar | TX | — | 250 MW | Planned, approvals not yet initiated | — |
| Oak Valley Solar (Unit OAK) | Solar | TX | — | 251 MW | Planned, approvals not yet initiated | — |
| Blue Hills Wind Project (Unit BHWP) | Wind (onshore) | TX | — | 276 MW | Regulatory approvals pending | — |
| Cazadores Solar (Unit 73509) | Solar | TX | — | 300 MW | Planned, approvals not yet initiated | — |
| Pease River Solar (Unit 58441) | Solar | TX | — | 300 MW | Planned, approvals not yet initiated | — |
| Black Bear Natural Gas Development | Other | TX | — | Not disclosed | Agency permitting | — |
| Piney Woods Development | Other | TX | — | Not disclosed | Agency permitting | — |
| Texas Gateway Project | Pipeline | TX | — | Not disclosed | Agency permitting | — |
| Project Matador Nuclear (Unit PMN1) | Nuclear | TX | — | Not disclosed | Planned, approvals not yet initiated | — |
| Project Matador Nuclear (Unit PMN2) | Nuclear | TX | — | Not disclosed | Planned, approvals not yet initiated | — |
| Project Matador Nuclear (Unit PMN4) | Nuclear | TX | — | Not disclosed | Planned, approvals not yet initiated | — |
| Project Matador Nuclear (Unit PMN3) | Nuclear | TX | — | Not disclosed | Planned, approvals not yet initiated | — |
| CCPL Expansion Project (Corpus Christi Stage IV) (Cheniere Corpus Christi Pipeline) | Pipeline | TX | — | 3,000 MMcf/d | Agency permitting | — |
| Apex (Targa Resources) | Pipeline | TX | — | 2,000 MMcf/d | Agency permitting | — |
| Bull Run Extension (Targa Resources) | Pipeline | TX | — | Not disclosed | Agency permitting | — |
| Buffalo Run (Targa Resources) | Pipeline | TX | — | Not disclosed | Planned, approvals not yet initiated | — |
| DeLa Express Project (DeLa Express LLC) | Pipeline | TX,LA | — | 2,000 MMcf/d | Agency permitting | — |
| Forza pipeline (Forza Pipeline LLC & Bull Run Pipeline LLC (Targa Resources)) | Pipeline | NM,TX | — | 750 MMcf/d | Agency permitting | — |
| NGPL Gulf Coast Southbound Project (Phase III) (Nat Gas P L Co of America) | Pipeline | IA,IL,MO,AR,TX | — | 260 MMcf/d | Agency permitting | — |
| Nueva Era Dos Pipeline Project (Nueva Era Pipeline LLC) | Pipeline | TX, MX | — | 1,000 MMcf/d | Agency permitting | — |
| Permian West Expansion (Kinder Morgan (El Paso Natural Gas)) | Pipeline | TX | — | 82 MMcf/d | Agency permitting | — |
| Texas Gateway Project (Gulf South Pipeline Co. LLC) | Pipeline | TX,LA | — | 1,450 MMcf/d | Agency permitting | — |
| Texas-Arkansas Power Project (TAPP) (Kinder Morgan (NGPL)) | Pipeline | TX,AR | — | 400 MMcf/d | Agency permitting | — |
| South Mississippi Project (Energy Transfer) | Pipeline | TX,LA,MS | — | 2,000 MMcf/d | Planned, approvals not yet initiated | — |
| Sabine Crossing Pipeline (Cheniere Energy (Sabine Crossing Pipeline, LLC)) | Pipeline | TX,LA | — | 2,500 MMcf/d | Agency permitting | — |
| Texas Access Project (Kinder Morgan Louisiana Pipeline LLC) | Pipeline | TX,LA | — | 1,300 MMcf/d | Agency permitting | — |
| Transco Wharton West project (Transcontinental Gas Pipe Line (Williams)) | Pipeline | TX | — | 310 MMcf/d | Agency permitting | — |
| Banita Creek- Spindlepop Solar (Unit MIDBS) | Storage | TX | — | 303 MW | Regulatory approvals pending | — |
| Rowdy Creek Solar and BESS (Unit RDYBS) | Storage | TX | — | 350 MW | Regulatory approvals pending | — |