BRAZOS ELECTRIC POWER COOPERATIVE, INC. (BRAZOS ELECTRIC) (TX PUCT Docket 58865)
Capacity
Not disclosed
Waiting
0.9 yrs
Stage
Local/state review
Verification
Verified (primary source)
Estimated investment waiting
Not estimated: Investment-waiting is only estimated for projects with capacity measured in MW (generation/storage). This project's capacity is measured differently (e.g. MTPA, or pipeline length/diameter).
Timeline
- Nov 6, 2025ORDER OF REFERRAL AND PRELIMINARY ORDER — PL
- Nov 13, 2025SOAH ORDER NO. 1 — PL
- Nov 21, 2025SOAH ORDER NO 2 — PL
- Dec 19, 2025SOAH ORDER NO. 3 — PL
- Jan 6, 2026SOAH ORDER NO. 4: - ORDER CANCELING HEARING AND REQUIRING STATUS REPORT — PL
- Feb 5, 2026ORDER GRANTING MOTION TO DISMISS — PL
- Feb 13, 2026ORDER NO. 1- ADDRESSING INTERVENTIONS — PL
- Feb 19, 2026Joint Response to Commission Order No. 1 — PL
- Mar 12, 2026ORDER NO. 2 - ADDRESSING INTERVENTIONS — PL
- Mar 23, 2026ORDER NO. 3 - ESTABLISHING DEADLINE — PL
- Apr 14, 2026ORDER NO. 4 - DISMISSING INTERVENORS — PL
Public Hearings
Unknown
Hearing details: Unknown
Not available from this project’s data source yet. Check the sources below directly.
Sources
Data quality note: Sourced from the Texas Public Utility Commission's public Interchange docket search. PUCT publishes no docket-level status field; "still waiting" here is inferred from the filing history (no final order, order on rehearing, or similar closing filing found) — see the ingestion module header for how this was calibrated and its known limits. No structured location field is published; this project will not appear on the map until geocoded another way.