BRAZOS ELECTRIC POWER COOPERATIVE, INC. (BRAZOS ELECTRIC) (TX PUCT Docket 58865)

TX

Capacity
Not disclosed
Waiting
0.9 yrs
Stage
Local/state review
Verification
Verified (primary source)

Estimated investment waiting

Not estimated: Investment-waiting is only estimated for projects with capacity measured in MW (generation/storage). This project's capacity is measured differently (e.g. MTPA, or pipeline length/diameter).

Timeline

  • Nov 6, 2025
    ORDER OF REFERRAL AND PRELIMINARY ORDERPL
  • Nov 13, 2025
    SOAH ORDER NO. 1PL
  • Nov 21, 2025
    SOAH ORDER NO 2PL
  • Dec 19, 2025
    SOAH ORDER NO. 3PL
  • Jan 6, 2026
    SOAH ORDER NO. 4: - ORDER CANCELING HEARING AND REQUIRING STATUS REPORTPL
  • Feb 5, 2026
    ORDER GRANTING MOTION TO DISMISSPL
  • Feb 13, 2026
    ORDER NO. 1- ADDRESSING INTERVENTIONSPL
  • Feb 19, 2026
    Joint Response to Commission Order No. 1PL
  • Mar 12, 2026
    ORDER NO. 2 - ADDRESSING INTERVENTIONSPL
  • Mar 23, 2026
    ORDER NO. 3 - ESTABLISHING DEADLINEPL
  • Apr 14, 2026
    ORDER NO. 4 - DISMISSING INTERVENORSPL

Public Hearings

Unknown

Hearing details: Unknown

Not available from this project’s data source yet. Check the sources below directly.

Sources

Data quality note: Sourced from the Texas Public Utility Commission's public Interchange docket search. PUCT publishes no docket-level status field; "still waiting" here is inferred from the filing history (no final order, order on rehearing, or similar closing filing found) — see the ingestion module header for how this was calibrated and its known limits. No structured location field is published; this project will not appear on the map until geocoded another way.