WaitingForPower
generation · Solar

Interconnection Request 27INR0221 (Solar+Battery)

Starr, TX

Developer: Rio Grande Solar LLC

Capacity
896 MW
Waiting
2.5 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
Facility Study
Grid region
ERCOT
Point of interconnection
Tap 345 kV 80355 Del Sol - 80119 Frontera Ckt 1

Estimated investment waiting

$1.19B

895,670 kW × $1,327/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.

Location

26.5309, -98.7402 — see the map for this project in context with others.

Public Hearings

Unknown

Hearing details: Unknown

Not available from this project’s data source yet. Check the sources below directly.

Sources

Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.