generation · Wind (onshore)
Interconnection Request 29INR0025 (Wind)
Pecos, TX
Developer: NextEra Energy Interconnection Holdings, LLC
Capacity
370 MW
Waiting
1.8 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
Facility Study
Grid region
ERCOT
Point of interconnection
138kV #38365 TNPINION
Estimated investment waiting
$635.7M
≈ 370,000 kW × $1,718/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.
Location
30.7733, -102.7182 — see the map for this project in context with others.
Timeline
- Dec 23, 2025Interconnection agreement executed — Interconnection agreement
Public Hearings
Unknown
Hearing details: Unknown
Not available from this project’s data source yet. Check the sources below directly.
Sources
Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.