generation · Solar
Interconnection Request 22INR0402 (Solar+Battery)
Swisher, TX
Developer: Hecate Energy Frye Storage LLC
Capacity
504 MW
Waiting
6.0 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
Facility Study
Grid region
ERCOT
Point of interconnection
new 345kV sub Kress connecting both 23912 Ogallala - 23914 Tule Canyon circuits
Estimated investment waiting
$668.6M
≈ 503,850 kW × $1,327/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.
Location
34.5263, -101.7439 — see the map for this project in context with others.
Public Hearings
Unknown
Hearing details: Unknown
Not available from this project’s data source yet. Check the sources below directly.
Sources
Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.