Capacity
366 MW
Waiting
0.7 yrs
Stage
Local/state review
Verification
Verified (primary source)
Estimated investment waiting
$413.6M
≈ 366,000 kW × $1,130/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.
Timeline
- Dec 10, 2025ORDER NO. 1 - REQUIRING RECOMMENDATION FROM COMMISSION STAFF ON SUFFICIENCY OF APPLICATION AND NOTICE, ADDRESSING OTHER PROCEDURAL MATTERS AND ENTERING PROTECTIVE ORDER — PL
- Jan 5, 2026ORDER NO. 2 - GRANTING MOTIONS TO INTERVENE — PL
- Jan 7, 2026ORDER NO. 3 - FINDING APPLICATION AND NOTICE SUFFICIENT AND REQUIRING PROCEDURAL SCHEDULE — PL
- Jan 14, 2026ORDER NO. 4 - GRANTING MOTION TO INTERVENE — PL
- Jan 22, 2026ORDER NO. 5- GRANTING EXTENSION — PL
- Jan 23, 2026ORDER REQUESTING LISTS OF ISSUES — PL
- Jan 30, 2026ORDER NO. 6- ESTABLISHING DEADLINES — PL
- Feb 19, 2026ORDER NO. 7 - GRANTING MOTION TO INTERVENE — PL
- Feb 25, 2026ORDER NO. 8 - GRANTING MOTION TO INTERVENE — PL
- Mar 11, 2026DRAFT PRELIMINARY ORDER AND MEMORANDUM — PL
- Mar 11, 2026ORDER OF REFERRAL — PL
- Mar 12, 2026PRELIMINARY ORDER — PL
- Mar 12, 2026OUTGOING COMMISSION-SIGNED ORDER MAIL LOG — PL
- Mar 20, 2026SOAH ORDER NO. 1- PROJECT DESCRIPTION; JURISDICTION; DEADLINE FOR DECISION; SETTING PREHEARING CONFERENCE; ADDRESSING GENERAL PROCEDURAL REQUIREMENTS — PL
- Apr 13, 2026SOAH ORDER NO. 2- MEMORIALIZING PREHEARING CONFERENCE; ADOPTING PROCEDURAL SCHEDULE; SCHEDULING HEARING ON THE MERITS; AND ADDRESSING HEARING PROCEDURES — PL
- Aug 6, 2026City of El Paso's Proposed Order — PL
Public Hearings
Unknown
Hearing details: Unknown
Not available from this project’s data source yet. Check the sources below directly.
Sources
Data quality note: Sourced from the Texas Public Utility Commission's public Interchange docket search. PUCT publishes no docket-level status field; "still waiting" here is inferred from the filing history (no final order, order on rehearing, or similar closing filing found) — see the ingestion module header for how this was calibrated and its known limits. Capacity figure is parsed from the case-style description text, not a structured field — not independently verified. No structured location field is published; this project will not appear on the map until geocoded another way.