generation · Solar
Interconnection Request 24INR0412 (Solar+Battery)
Houston, TX
Developer: Camino Ranch Solar Project LLC
Capacity
296 MW
Waiting
3.9 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
Facility Study
Grid region
ERCOT
Point of interconnection
Tap to Jim English (#3351) – Flat Branch (#3345) 138kV
Estimated investment waiting
$393.3M
≈ 296,420 kW × $1,327/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.
Location
31.3230, -95.4216 — see the map for this project in context with others.
Timeline
- Dec 31, 2025Interconnection agreement executed — Interconnection agreement
Public Hearings
Unknown
Hearing details: Unknown
Not available from this project’s data source yet. Check the sources below directly.
Sources
Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.