generation · Solar
Interconnection Request 28INR0005 (Solar)
Zapata, TX
Developer: NextEra Energy Interconnection Holdings LLC
Capacity
359 MW
Waiting
3.1 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
Facility Study
Grid region
ERCOT
Point of interconnection
TAP 345kV 80307 Del Sol 7C - 80225 Cenizo 7C
Estimated investment waiting
$476.4M
≈ 359,000 kW × $1,327/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.
Location
26.9970, -99.1826 — see the map for this project in context with others.
Public Hearings
Unknown
Hearing details: Unknown
Not available from this project’s data source yet. Check the sources below directly.
Sources
Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.