Capacity
Not disclosed
Waiting
2.2 yrs
Stage
Local/state review
Verification
Verified (primary source)
Estimated investment waiting
Not estimated: Investment-waiting is only estimated for projects with capacity measured in MW (generation/storage). This project's capacity is measured differently (e.g. MTPA, or pipeline length/diameter).
Timeline
- Jun 17, 2024ORDER NO. 1 - REQUIRING INFORMATION FROM APPLICANT AND RECOMMENDATION FROM COMMISSION STAFF ON SUFFICIENCY OF APPLICATION AND NOTICE, AND ADDRESSING OTHER PROCEDURAL MATTERS — PL
- Jun 18, 2024Lone Star Transmission, LLC's Response to Order No. 1 Standard CCN Questions. — PL
- Jul 2, 2024ORDER NO. 2 - GRANTING EXTENSION AND AMENDING PROCEDURAL SCHEDULE — PL
- Jul 16, 2024ORDER NO. 3 - FINDING APPLICATION ADMINISTRATIVELY COMPLETE, NOTICE SUFFICIENT, FINDING RESPONSES SUFFICIENT, AND REQUIRING JOINT PROPOSED PROCEDURAL SCHEDULE FOR FURTHER PROCESSING — PL
- Jul 31, 2024ORDER NO. 4 - ESTABLISHING PROCEDURAL SCHEDULE FOR CONTINUED PROCESSING — PL
- Aug 19, 2024ORDER NO. 5 - ADMITTING EVIDENCE — PL
Public Hearings
Unknown
Hearing details: Unknown
Not available from this project’s data source yet. Check the sources below directly.
Sources
Data quality note: Sourced from the Texas Public Utility Commission's public Interchange docket search. PUCT publishes no docket-level status field; "still waiting" here is inferred from the filing history (no final order, order on rehearing, or similar closing filing found) — see the ingestion module header for how this was calibrated and its known limits. No structured location field is published; this project will not appear on the map until geocoded another way.