WaitingForPower
generation · Solar

Interconnection Request 26INR0603 (Solar+Battery)

Eastland, TX

Developer: Damia Solar, LLC

Capacity
306 MW
Waiting
1.4 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
Facility Study
Grid region
ERCOT
Point of interconnection
Tap 138kV 6317 Cisco - 3545 MTNBRANCH_8

Estimated investment waiting

$406.1M

306,000 kW × $1,327/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.

Location

32.3246, -98.8366 — see the map for this project in context with others.

Public Hearings

Unknown

Hearing details: Unknown

Not available from this project’s data source yet. Check the sources below directly.

Sources

Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.