Capacity
Not disclosed
Waiting
2.5 yrs
Stage
Local/state review
Verification
Verified (primary source)
Estimated investment waiting
Not estimated: Investment-waiting is only estimated for projects with capacity measured in MW (generation/storage). This project's capacity is measured differently (e.g. MTPA, or pipeline length/diameter).
Timeline
- Feb 26, 2024ORDER NO. 1 - REQUIRING INFORMATION FROM APPLICANT; REQUIRING RECOMMENDATIONS FROM COMMISSION STAFF ON SUFFICIENCY OF APPLICATION, NOTICE, AND REQUESTED EXCEPTIONS; AND ADDRESSING OTHER PROCEDURAL MATTERS — PL
- Mar 6, 2024Rayburn Country Electric Cooperative's Responses to Commission Order No. 1 — PL
- Mar 8, 2024ORDER NO. 2 - GRANTING INTERVENTION — PL
- Mar 20, 2024ORDER NO. 3 - GRANTING INTERVENTIONS AND SETTING DEADLINE — PL
- Mar 21, 2024ORDER NO. 4 - GRANTING EXTENSION, IN PART — PL
- Mar 22, 2024COMMISSION STAFF’S RESPONSE TO ORDER NO. 3 — PL
- Mar 27, 2024ORDER NO. 5 - DEFERRING RULING ON ADMINISTRATIVE COMPLETENESS — PL
- Apr 29, 2024Rayburn Country Electric Cooperative Inc.'s Motion for Protective Order — PL
- May 15, 2024ORDER NO. 6 - GRANTING MOTION TO LEAVE — PL
- Jun 26, 2024ORDER NO. 7 - ENTERING PROTECTIVE ORDER — PL
- Sep 4, 2024ORDER NO. 8 - GRANTING MOTION TO WITHDRAW, DISMISSING APPLICATION WITHOUT PREJUDICE, AND CLOSING DOCKET — PL
Public Hearings
Unknown
Hearing details: Unknown
Not available from this project’s data source yet. Check the sources below directly.
Sources
Data quality note: Sourced from the Texas Public Utility Commission's public Interchange docket search. PUCT publishes no docket-level status field; "still waiting" here is inferred from the filing history (no final order, order on rehearing, or similar closing filing found) — see the ingestion module header for how this was calibrated and its known limits. No structured location field is published; this project will not appear on the map until geocoded another way.