WaitingForPower
generation · Solar

Interconnection Request 28INR0179 (Solar+Battery)

San Patricio, TX

Developer: Indigo Solar, LLC

Capacity
302 MW
Waiting
1.9 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
Facility Study
Grid region
ERCOT
Point of interconnection
Tap LONHILL (Bus#8455) to KATOEN (Bus#8579).

Estimated investment waiting

$400.2M

301,600 kW × $1,327/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.

Location

28.0118, -97.5172 — see the map for this project in context with others.

Public Hearings

Unknown

Hearing details: Unknown

Not available from this project’s data source yet. Check the sources below directly.

Sources

Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.