WaitingForPower
generation · Gas

Interconnection Request 28INR0086 (Gas)

Upton, TX

Developer: Invenergy Energy Transition Development LLC

Capacity
888 MW
Waiting
2.2 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
Facility Study
Grid region
ERCOT
Point of interconnection
Tap 345kV 76000 L_NORTMC5_1Y - 18668 ROCKDRAW_5

Estimated investment waiting

$1.00B

888,000 kW × $1,130/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.

Location

31.3538, -102.0415 — see the map for this project in context with others.

Public Hearings

Unknown

Hearing details: Unknown

Not available from this project’s data source yet. Check the sources below directly.

Sources

Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.