Capacity
Not disclosed
Waiting
1.4 yrs
Stage
Local/state review
Verification
Verified (primary source)
Estimated investment waiting
Not estimated: Investment-waiting is only estimated for projects with capacity measured in MW (generation/storage). This project's capacity is measured differently (e.g. MTPA, or pipeline length/diameter).
Timeline
- Apr 30, 2025ORDER OF REFERRAL AND PRELIMINARY ORDER — PL
- Apr 30, 2025SOAH ORDER NO. 1 - PROJECT DESCRIPTION; JURISDICTION, DEADLINE FOR DECISION, INTERVENTION DEADLINE; COMMENTS ON SUFFICIENCY OF APPLICATION AND NOTICE; SETTING PREHEARING CONFERENCE; CAUTION TO INTERESTED PARTIES; AND GENERAL PROCEDURAL REQUIREMENTS — PL
- May 9, 2025SOAH ORDER NO. 2 - CANCELING PREHEARING CONFERENCE AND ADOPTING PROCEDURAL SCHEDULE; SETTING HEARING ON THE MERITS AND REQUIRING PRE- AND POST- HEARING EXHIBIT PROCEDURES — PL
- Jun 2, 2025SOAH ORDER NO. 3 - FINDING APPLICATION AND NOTICE SUFFICIENT; SETTING DEADLINE TO RESPOND TO MOTION TO INTERVENE; AND DETERMINING ROUTE ADEQUACY HEARING IS NOT NEEDED — PL
- Jun 4, 2025SOAH ORDER NO. 4 - GRANTING INTERVENTION — PL
- Jun 27, 2025SOAH ORDER NO. 5 - GRANTING JOINT MOTION TO ABATE — PL
- Jul 24, 2025SOAH ORDER NO. 6 - CANCELING PROCEDURAL SCHEDULE, ADMITTING EVIDENCE, AND REMANDING TO THE COMMISSION — PL
Public Hearings
Unknown
Hearing details: Unknown
Not available from this project’s data source yet. Check the sources below directly.
Sources
Data quality note: Sourced from the Texas Public Utility Commission's public Interchange docket search. PUCT publishes no docket-level status field; "still waiting" here is inferred from the filing history (no final order, order on rehearing, or similar closing filing found) — see the ingestion module header for how this was calibrated and its known limits. No structured location field is published; this project will not appear on the map until geocoded another way.