generation · Wind (onshore)
Interconnection Request 27INR0132 (Wind+Battery)
San Patricio, TX
Developer: RWE Clean Energy Development, LLC
Capacity
298 MW
Waiting
2.4 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
Facility Study
Grid region
ERCOT
Point of interconnection
Tap 345kV 8624 Grissom – 8455 Lon C Hill
Estimated investment waiting
$511.1M
≈ 297,500 kW × $1,718/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.
Location
28.0118, -97.5172 — see the map for this project in context with others.
Timeline
- Dec 19, 2025Interconnection agreement executed — Interconnection agreement
Public Hearings
Unknown
Hearing details: Unknown
Not available from this project’s data source yet. Check the sources below directly.
Sources
Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.