Pecos, TX

Developer: Selenite Springs Solar, LLC

Capacity
300 MW
Waiting
1.4 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
Facility Study
Grid region
ERCOT
Point of interconnection
Tap 138kV 38355 Leon Creek Switching Station - 38308 Woodhouse Switching Station

Estimated investment waiting

$398.1M

300,000 kW × $1,327/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.

Location

30.7733, -102.7182 — see the map for this project in context with others.

Timeline

  • Dec 24, 2025
    Interconnection agreement executedInterconnection agreement

Public Hearings

Unknown

Hearing details: Unknown

Not available from this project’s data source yet. Check the sources below directly.

Sources

Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.