WaitingForPower
generation · Solar

Interconnection Request 26INR0110 (Solar+Battery)

Crane, TX

Developer: Hecate Energy Point Mountain Solar Facility 1 LLC

Capacity
410 MW
Waiting
3.4 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
Facility Study
Grid region
ERCOT
Point of interconnection
Tap 138 kV 76615 Crane -76635 King Mountain; POI is 7.85 miles from Crane.

Estimated investment waiting

$544.3M

410,200 kW × $1,327/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.

Location

31.4396, -102.4925 — see the map for this project in context with others.

Public Hearings

Unknown

Hearing details: Unknown

Not available from this project’s data source yet. Check the sources below directly.

Sources

Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.