Capacity
150 MW
Waiting
0.4 yrs
Stage
Local/state review
Verification
Verified (primary source)
Estimated investment waiting
$197.4M
≈ 150,000 kW × $1,316/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.
Timeline
- Apr 1, 2026ORDER NO. 1 - REQUIRING RECOMMENDATION FROM COMMISSION STAFF ON SUFFICIENCY OF APPLICATION AND NOTICE, ADDRESSING OTHER PROCEDURAL MATTERS AND ENTERING PROTECTIVE ORDER — PL
- Apr 2, 2026ORDER REQUESTING LISTS OF ISSUES — PL
- Apr 27, 2026ORDER NO. 2 - FINDING APPLICATION ADMINISTRATIVELY COMPLETE, REQUIRING SUPPLEMETNAL RECOMMENDATION, GRANTING MOTION TO EXTEND TIME AND GRANTING MOTION TO INTERVENE — PL
- Apr 29, 2026DRAFT PRELIMINARY ORDER WITH MEMORANDUM — PL
- May 6, 2026ORDER OF REFERRAL — PL
- May 7, 2026PRELIMINARY ORDER — PL
- May 7, 2026OUTGOING COMMISSION-SIGNED ORDER MAIL LOG — PL
- May 12, 2026SOAH ORDER NO. 1- FILING DESCRIPTION, JURISDICTION, SUFFICIENCY OF NOTICE, REQUIRING FILING, AND ADDRESSING GENERAL PROCEDURES — PL
- Jun 15, 2026SOAH ORDER NO. 2- CONSOLIDATING CASES; ADOPTING PROCEDURAL SCHEDULE; SETTING HEARING ON THE MERITS; AND ADDRESSING HEARING PROCEDURES — PL
Public Hearings
Unknown
Hearing details: Unknown
Not available from this project’s data source yet. Check the sources below directly.
Sources
Data quality note: Sourced from the Texas Public Utility Commission's public Interchange docket search. PUCT publishes no docket-level status field; "still waiting" here is inferred from the filing history (no final order, order on rehearing, or similar closing filing found) — see the ingestion module header for how this was calibrated and its known limits. Capacity figure is parsed from the case-style description text, not a structured field — not independently verified. No structured location field is published; this project will not appear on the map until geocoded another way.