transmission · Transmission
BRAZOS ELECTRIC POWER COOPERATIVE, INC. (BRAZOS ELECTRIC) (TX PUCT Docket 59913)
Capacity
Not disclosed
Waiting
0.2 yrs
Stage
Local/state review
Verification
Verified (primary source)
Estimated investment waiting
Not estimated: Investment-waiting is only estimated for projects with capacity measured in MW (generation/storage). This project's capacity is measured differently (e.g. MTPA, or pipeline length/diameter).
Timeline
- Jul 8, 2026ORDER NO. 1 - REQUIRING RECOMMENDATION FROM COMMISSION STAFF ON SUFFICIENCY OF APPLICATION AND NOTICE, AND ADDRESSING OTHER PROCEDURAL MATTERS — PL
- Jul 15, 2026Responses to Standard Order No. 1 Questions — PL
- Jul 27, 2026ORDER NO. 2 - GRANTING EXTENSION — PL
- Jul 29, 2026ORDER NO. 3- GRANTING MOTIONS TO INTERVENE — PL
- Jul 29, 2026Brazos Electric's Motion for Entry of Protective Order — PL
- Jul 31, 2026ORDER NO. 4- FINDING APPLICATION ADMINISTRATIVELY COMPLETE, FINDING NOTICE SUFFICIENT, FINDING RESPONSES SUFFICIENT, ESTABLISHING PROCEDURAL SCHEDULE, AND ENTERING PROTECTIVE ORDER — PL
Public Hearings
Unknown
Hearing details: Unknown
Not available from this project’s data source yet. Check the sources below directly.
Sources
Data quality note: Sourced from the Texas Public Utility Commission's public Interchange docket search. PUCT publishes no docket-level status field; "still waiting" here is inferred from the filing history (no final order, order on rehearing, or similar closing filing found) — see the ingestion module header for how this was calibrated and its known limits. No structured location field is published; this project will not appear on the map until geocoded another way.