Capacity
250 MW
Waiting
1.9 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
System Impact Study
Grid region
SPP
Point of interconnection
Tuco - Whirlwind 345 kV Line
Queue cluster
DISIS-2024-001; 05 SOUTHWEST
Estimated investment waiting
$429.5M
≈ 250,000 kW × $1,718/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.
Location
34.0737, -101.3033 — see the map for this project in context with others.
Public Hearings
Unknown
Hearing details: Unknown
Not available from this project’s data source yet. Check the sources below directly.
Sources
Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.