BROWNSVILLE PUBLIC UTILITIES BOARD (TX PUCT Docket 57750)

TX

Capacity
Not disclosed
Waiting
1.5 yrs
Stage
Local/state review
Verification
Verified (primary source)

Estimated investment waiting

Not estimated: Investment-waiting is only estimated for projects with capacity measured in MW (generation/storage). This project's capacity is measured differently (e.g. MTPA, or pipeline length/diameter).

Timeline

  • Feb 26, 2025
    ORDER NO. 1 - REQUIRING COMMENTS ON SUFFICIENCY OF APPLICATION AND NOTICE AND ESTABLISHING PROCEDURAL SCHEDULEPL
  • Mar 27, 2025
    ORDER NO. 2 - FINDING APPLICATION ADMINISTRATIVELY COMPLETE AND NOTICE SUFFICIENTPL
  • Apr 16, 2025
    ORDER NO. 3 - AMENDING PROCEDURAL SCHEDULE AND SOLICITING MOTION TO ADMIT EVIDENCEPL
  • Apr 25, 2025
    ORDER NO. 4 - DENYING EXTENSIONPL
  • Apr 29, 2025
    ORDER NO. 5 - GRANTING EXTENSIONPL
  • May 8, 2025
    ORDER NO 6. - ADMITTING EVIDENCEPL

Public Hearings

Unknown

Hearing details: Unknown

Not available from this project’s data source yet. Check the sources below directly.

Sources

Data quality note: Sourced from the Texas Public Utility Commission's public Interchange docket search. PUCT publishes no docket-level status field; "still waiting" here is inferred from the filing history (no final order, order on rehearing, or similar closing filing found) — see the ingestion module header for how this was calibrated and its known limits. No structured location field is published; this project will not appear on the map until geocoded another way.