WaitingForPower
generation · Solar

Interconnection Request 26INR0609 (Solar)

Milam, TX

Developer: Ben Milam Solar 4

Capacity
600 MW
Waiting
1.7 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
Facility Study
Grid region
ERCOT
Point of interconnection
3377 LTPSW 345KV

Estimated investment waiting

$796.2M

600,000 kW × $1,327/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.

Location

30.7912, -96.9844 — see the map for this project in context with others.

Public Hearings

Unknown

Hearing details: Unknown

Not available from this project’s data source yet. Check the sources below directly.

Sources

Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.