WaitingForPower
generation · Solar

Interconnection Request 24INR0423 (Solar+Battery)

Leon, TX

Developer: Hollow Branch Creek Solar LLC

Capacity
460 MW
Waiting
4.0 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
Facility Study
Grid region
ERCOT
Point of interconnection
Jewett – Singleton 345 kV [PTI Bus # 3390 – 44645]

Estimated investment waiting

$610.4M

460,000 kW × $1,327/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.

Location

31.3005, -95.9956 — see the map for this project in context with others.

Public Hearings

Unknown

Hearing details: Unknown

Not available from this project’s data source yet. Check the sources below directly.

Sources

Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.