WaitingForPower

Ohio energy projects waiting for approval

36 projects currently waiting on a permitting decision in Ohio, tracked live from public federal and state sources. See every state →

36
Projects
3,329 MW
Capacity waiting
1,371 MW
Clean energy capacity waiting
3/36 projects are zero-carbon generation
$4.08B
Est. investment waiting
6/36 projects have an applicable estimate
Documented estimates, not precise figures. See methodology.
36 projects
Project Fuel Location Waiting Capacity Stage Queue stage
AEP Interconnection Request AG1-410 (Solar)SolarOH5.9 yrs300 MWInterconnection studySystem Impact Study
Darrow-Riverway and Evans-Riverway 138 kV Transmission Line Project (OH OPSB Case 22-0250-EL-BTX)TransmissionOH4.1 yrsNot disclosedPlanned, approvals not yet initiated
DEOK Interconnection Request AI1-167 (Battery)StorageOH4.0 yrs250 MWInterconnection studyFeasibility Study
AEP Interconnection Request AI2-081 (Solar)SolarOH3.5 yrs271 MWInterconnection studyFeasibility Study
DEOK Interconnection Request AJ1-008 (Solar+Battery)SolarOH3.3 yrs800 MWInterconnection studyFeasibility Study
Carnation Solar (OH OPSB Case 24-0881-EL-BGN)SolarOH2.0 yrsNot disclosedLocal/state review
Elliott-Lee 138 kV Transmission Line Rebuild Project (OH OPSB Case 24-0978-EL-BTX)TransmissionOH1.9 yrsNot disclosedLocal/state review
ATSI Interconnection Request AH1-680 (Gas)GasOH1.4 yrs1,300 MWInterconnection studySystem Impact Study
ATSI Interconnection Request AH1-711 (Gas)GasOH1.4 yrs408 MWInterconnection studySystem Impact Study
Woodward Park North Columbus High Pressure (NCHP) System Pipeline Project (OH OPSB Case 25-0838-GA-BTX)PipelineOH1.0 yrsNot disclosedLocal/state review
Chestnut Run Energy Transmission Line (OH OPSB Case 25-1066-EL-BTX)TransmissionOH0.8 yrsNot disclosedLocal/state review
South Coshocton-Wooster 138 kV Transmission Line Rebuild (West Millersburg-Wooster) (OH OPSB Case 26-0128-EL-BTX)TransmissionOH0.5 yrsNot disclosedPlanned, approvals not yet initiated
Fairfield Energy Center (OH OPSB Case 26-0160-EL-BGN)GasOH0.5 yrsNot disclosedLocal/state review
Beatty Road-Canal Street 138 kV Transmission Line Rebuild (OH OPSB Case 26-0073-EL-BTX)TransmissionOH0.5 yrsNot disclosedPlanned, approvals not yet initiated
Ashville Energy Center (OH OPSB Case 26-196-EL-BGN)GasOH0.5 yrsNot disclosedLocal/state review
CPV Walker Energy Center (OH OPSB Case 26-0353-EL-BGN)GasOH0.4 yrsNot disclosedPlanned, approvals not yet initiated
PowerConneX New Albany 3 Energy Center (OH OPSB Case 26-361-EL-BGN)GasOH0.4 yrsNot disclosedLocal/state review
Baku-Gavin 765 kV Transmission Line (OH OPSB Case 26-0426-EL-BTX)TransmissionOH0.4 yrsNot disclosedLocal/state review
Barr Energy Center (OH OPSB Case 26-0498-EL-BGN)StorageOH0.4 yrsNot disclosedPlanned, approvals not yet initiated
Neo Power Generation Facility (OH OPSB Case 26-0627-EL-BGN)GasOH0.3 yrsNot disclosedLocal/state review
Butterfly Meadows Solar (OH OPSB Case 26-670-EL-BGN)SolarOH0.3 yrsNot disclosedPlanned, approvals not yet initiated
PORTS Energy Center (OH OPSB Case 26-0746-EL-BGN)GasOH0.1 yrsNot disclosedLocal/state review
Hanging Rock-Baku 765 kV Transmission Line (OH OPSB Case 26-0870-EL-BTX)TransmissionOH0.1 yrsNot disclosedPlanned, approvals not yet initiated
Grid Growth West Thistlewood-Beatty 345 kV Transmission Line Project (OH OPSB Case 26-0811-EL-BTX)TransmissionOH0.0 yrsNot disclosedPlanned, approvals not yet initiated
Grid Growth West Greentown-Thistlewood 765 kV Transmission Line Project (OH OPSB Case 26-0809-EL-BTX)TransmissionOH0.0 yrsNot disclosedPlanned, approvals not yet initiated
Grid Growth East Adkins-West Millersport 765 kV Transmission Line Project (OH OPSB Case 26-0813-EL-BTX)TransmissionOH0.0 yrsNot disclosedPlanned, approvals not yet initiated
Grid Growth East Conesville-Guernsey 765 kV Transmission Line Project (OH OPSB Case 26-0812-EL-BTX)TransmissionOH0.0 yrsNot disclosedPlanned, approvals not yet initiated
Grid Growth West Thistlewood-Marysville 765 kV Transmission Line Project (OH OPSB Case 26-0810-EL-BTX)TransmissionOH0.0 yrsNot disclosedPlanned, approvals not yet initiated
Borealis Project (Texas Gas Transmission)PipelineOH2,000 MMcf/dPlanned, approvals not yet initiated
Carnation Project (Texas Gas Transmission (Boardwalk))PipelineOH170 MMcf/dAgency permitting
Dearborn County Lateral (Texas Gas Transmission LLC)PipelineIN,KY,OH265 MMcf/dAgency permitting
Clarington Connector (EQT Corp.)PipelineOH,PA400 MMcf/dPlanned, approvals not yet initiated
Crossroads Expansion Project (Crossroads Pipeline Co. (TC Energy))PipelineOH,IN1,500 MMcf/dPlanned, approvals not yet initiated
Aspire Energy Express (Aspire Energy Express LLC)PipelineOH300 MMcf/dPlanned, approvals not yet initiated
Northern Loop Project (Columbia Gas of Ohio)PipelineOHNot disclosedAgency permitting
NKY Gate Enhancement Project (TC Energy (Columbia Gas Transmission))PipelineKY,OH0 MMcf/dAgency permitting