| AEP Interconnection Request AF1-204 (Wind) | Wind (onshore) | IN | 7.0 yrs | 255 MW | Interconnection study | System Impact Study |
| AEP Interconnection Request AG1-226 (Solar) | Solar | IN | 6.0 yrs | 450 MW | Interconnection study | Feasibility Study |
| HOOSIER ENERGY Interconnection Request J2270 (Solar) | Solar | IN | 5.1 yrs | 300 MW | Interconnection study | Cluster Study |
| INDIANAPOLIS POWER & LIGHT COMPANY Interconnection Request R1011 (Solar+Other+Battery) | Solar | IN | 4.9 yrs | 250 MW | Interconnection study | — |
| AEP Interconnection Request AH2-112 (Solar+Battery) | Solar | IN | 4.5 yrs | 250 MW | Interconnection study | Feasibility Study |
| AEP Interconnection Request AH2-257 (Solar) | Solar | IN | 4.5 yrs | 400 MW | Interconnection study | Feasibility Study |
| AEP Interconnection Request AH2-348 (Solar) | Solar | IN | 4.5 yrs | 700 MW | Interconnection study | Feasibility Study |
| AEP Interconnection Request AH2-352 (Solar) | Solar | IN | 4.5 yrs | 400 MW | Interconnection study | Feasibility Study |
| AEP Interconnection Request AH2-413 (Solar+Battery) | Solar | IN | 4.5 yrs | 365 MW | Interconnection study | Feasibility Study |
| AEP Interconnection Request AH2-414 (Battery) | Storage | IN | 4.5 yrs | 350 MW | Interconnection study | Feasibility Study |
| NORTHERN INDIANA PUBLIC SERVICE COMPANY Interconnection Request J2215 (Battery) | Storage | IN | 4.5 yrs | 300 MW | Interconnection study | Cluster Study |
| AEP Interconnection Request AI1-022 (Battery) | Storage | IN | 4.4 yrs | 450 MW | Interconnection study | Feasibility Study |
| AEP Interconnection Request AI1-085 (Solar) | Solar | IN | 4.1 yrs | 290 MW | Interconnection study | Feasibility Study |
| NORTHERN INDIANA PUBLIC SERVICE COMPANY Interconnection Request J2496 (Battery) | Storage | IN | 4.0 yrs | 400 MW | Interconnection study | Cluster Study |
| DUKE ENERGY INDIANA Interconnection Request J2581 (Battery) | Storage | IN | 4.0 yrs | 250 MW | Interconnection study | Cluster Study |
| NORTHERN INDIANA PUBLIC SERVICE COMPANY Interconnection Request J2846 (Solar) | Solar | IN | 4.0 yrs | 700 MW | Interconnection study | Cluster Study |
| Southern Indiana Gas & Electric Company d/b/a Centerpoint Energy Indiana South Interconnection Request J2970 (Solar) | Solar | IN | 4.0 yrs | 250 MW | Interconnection study | Cluster Study |
| HOOSIER ENERGY Interconnection Request J3075 (Solar+Battery) | Solar | IN | 4.0 yrs | 560 MW | Interconnection study | Cluster Study |
| Southern Indiana Gas & Electric Company d/b/a Centerpoint Energy Indiana South Interconnection Request J3077 (Solar+Battery) | Solar | IN | 4.0 yrs | 250 MW | Interconnection study | Cluster Study |
| DUKE ENERGY INDIANA Interconnection Request R1044 (Gas+Other) | Gas | IN | 2.6 yrs | 1,040 MW | Interconnection study | — |
| DUKE ENERGY INDIANA Interconnection Request J3232 (Gas) | Gas | IN | 2.4 yrs | 500 MW | Interconnection study | In Progress (unknown study) |
| INDIANAPOLIS POWER & LIGHT COMPANY Interconnection Request J3331 (Gas) | Gas | IN | 2.4 yrs | 470 MW | Interconnection study | In Progress (unknown study) |
| INDIANAPOLIS POWER & LIGHT COMPANY Interconnection Request J3666 (Gas) | Gas | IN | 2.4 yrs | 379 MW | Interconnection study | In Progress (unknown study) |
| DUKE ENERGY INDIANA Interconnection Request J3604 (Gas) | Gas | IN | 2.4 yrs | 650 MW | Interconnection study | In Progress (unknown study) |
| Interconnection Request J3564 (Wind) | Wind (onshore) | IN | 2.4 yrs | 275 MW | Interconnection study | In Progress (unknown study) |
| DUKE ENERGY INDIANA Interconnection Request J3834 (Battery) | Storage | IN | 2.0 yrs | 300 MW | Interconnection study | — |
| NORTHERN INDIANA PUBLIC SERVICE COMPANY Interconnection Request R5062 (Gas) | Gas | IN | 1.7 yrs | 733 MW | Interconnection study | — |
| NORTHERN INDIANA PUBLIC SERVICE COMPANY Interconnection Request J3846 (Wind) | Wind (onshore) | IN | 1.7 yrs | 275 MW | Interconnection study | — |
| AEP Interconnection Request AG2-072 (Gas) | Gas | IN | 1.6 yrs | 700 MW | Interconnection study | System Impact Study |
| NORTHERN INDIANA PUBLIC SERVICE COMPANY Interconnection Request J3931 (Solar) | Solar | IN | 1.6 yrs | 500 MW | Interconnection study | — |
| AEP Interconnection Request AG2-029 (Solar) | Solar | IN | 1.6 yrs | 250 MW | Interconnection study | System Impact Study |
| Duke Energy Indiana, LLC (IN IURC Cause No. 46193) | Gas | IN | 1.6 yrs | 738 MW | Litigation | — |
| AEP Interconnection Request AG2-163 (Solar) | Solar | IN | 1.6 yrs | 250 MW | Interconnection study | System Impact Study |
| DUKE ENERGY INDIANA Interconnection Request J3942 (Solar) | Solar | IN | 1.5 yrs | 365 MW | Interconnection study | — |
| DUKE ENERGY INDIANA Interconnection Request J3943 (Solar) | Solar | IN | 1.5 yrs | 337 MW | Interconnection study | — |
| NORTHERN INDIANA PUBLIC SERVICE COMPANY Interconnection Request J3910 (Wind) | Wind (onshore) | IN | 1.5 yrs | 300 MW | Interconnection study | — |
| DUKE ENERGY INDIANA Interconnection Request J3999 (Gas) | Gas | IN | 1.4 yrs | 1,540 MW | Interconnection study | — |
| INDIANAPOLIS POWER & LIGHT COMPANY Interconnection Request J4005 (Gas) | Gas | IN | 1.4 yrs | 500 MW | Interconnection study | — |
| INDIANAPOLIS POWER & LIGHT COMPANY Interconnection Request J4021 (Gas) | Gas | IN | 1.3 yrs | 470 MW | Interconnection study | — |
| AES Indiana Interconnection Request E0021 (Battery) | Storage | IN | 1.1 yrs | 310 MW | Interconnection study | In Progress (unknown study) |
| NIPSCO Interconnection Request E0033 (Battery) | Storage | IN | 1.1 yrs | 527 MW | Interconnection study | In Progress (unknown study) |
| NIPSCO Interconnection Request E0035 (Gas) | Gas | IN | 1.1 yrs | 1,090 MW | Interconnection study | In Progress (unknown study) |
| NIPSCO Interconnection Request E0042 (Gas) | Gas | IN | 1.1 yrs | 2,740 MW | Interconnection study | In Progress (unknown study) |
| Indiana Municipal Power Agency (IMPA) Interconnection Request E0046 (Gas) | Gas | IN | 1.1 yrs | 268 MW | Interconnection study | In Progress (unknown study) |
| DUKE ENERGY INDIANA Interconnection Request J3084 (Gas) | Gas | IN | 1.1 yrs | 642 MW | Interconnection study | Cluster Study |
| NIPSCO Interconnection Request E0039 (Battery) | Storage | IN | 1.1 yrs | 630 MW | Interconnection study | In Progress (unknown study) |
| DUKE ENERGY INDIANA Interconnection Request J4063 (Wind) | Wind (onshore) | IN | 1.0 yrs | 300 MW | Interconnection study | — |
| Hallador Power Interconnection Request E0054 (Gas+Battery) | Storage | IN | 0.8 yrs | 530 MW | Interconnection study | In Progress (unknown study) |
| HOOSIER ENERGY Interconnection Request J3114 (Solar+Battery) | Solar | IN | 0.8 yrs | 300 MW | Interconnection study | Cluster Study |
| Hoosier Energy Interconnection Request APP-100245 (Solar+Battery) | Solar | IN | 0.7 yrs | 405 MW | Interconnection study | In Progress (unknown study) |
| Hoosier Energy Interconnection Request APP-100248 (Solar+Battery) | Solar | IN | 0.7 yrs | 280 MW | Interconnection study | In Progress (unknown study) |
| Indiana Michigan Power Company (IN IURC Cause No. 46389) | Other | IN | 0.4 yrs | 918 MW | Local/state review | — |
| Indiana Michigan Power Company (IN IURC Cause No. 46443) | Gas | IN | 0.1 yrs | 1,520 MW | Local/state review | — |
| Patoka Solar (Unit 11101) | Solar | IN | — | 250 MW | Planned, approvals not yet initiated | — |
| Dearborn County Lateral (Texas Gas Transmission LLC) | Pipeline | IN,KY,OH | — | 265 MMcf/d | Agency permitting | — |
| Crossroads Expansion Project (Crossroads Pipeline Co. (TC Energy)) | Pipeline | OH,IN | — | 1,500 MMcf/d | Planned, approvals not yet initiated | — |
| Vector Pipeline Expansion (Vector Pipeline (DT Midstream / Enbridge JV)) | Pipeline | IN,MI,IL | — | 400 MMcf/d | Agency permitting | — |
| Sycamore Riverside Energy, LLC (Unit SYRVS) | Gas | IN | — | 964 MW | Planned, approvals not yet initiated | — |