WaitingForPower
storage · Storage

AES Indiana Interconnection Request E0021 (Battery)

Boone, IN

Developer: Brickyard Energy Storge, LLC

Capacity
310 MW
Waiting
1.1 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
In Progress (unknown study)
Grid region
MISO
Point of interconnection
Hortonville-Whitestown 345kV

Estimated investment waiting

$407.9M

309,960 kW × $1,316/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.

Location

40.0509, -86.4690 — see the map for this project in context with others.

Public Hearings

Unknown

Hearing details: Unknown

Not available from this project’s data source yet. Check the sources below directly.

Sources

Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.