WaitingForPower
generation · Solar

Hoosier Energy Interconnection Request APP-100248 (Solar+Battery)

Vigo, IN

Developer: Hoosier Energy / Solvenz

Capacity
280 MW
Waiting
0.7 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
In Progress (unknown study)
Grid region
MISO
Point of interconnection
Wabash River - Whitesville South 230 kV

Estimated investment waiting

$371.2M

279,720 kW × $1,327/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.

Location

39.4309, -87.3910 — see the map for this project in context with others.

Public Hearings

Unknown

Hearing details: Unknown

Not available from this project’s data source yet. Check the sources below directly.

Sources

Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.