91 projects currently waiting on a permitting decision in Illinois, tracked live from public federal and state sources. See every state →
91
Projects
26,592 MW
Capacity waiting
19,251 MW
Clean energy capacity waiting
60/91 projects are zero-carbon generation
$38.09B
Est. investment waiting
82/91 projects have an applicable estimate
Documented estimates, not precise figures. See methodology.
91 projects
| Project | Fuel | Location | Waiting ↓ | Capacity | Stage | Queue stage |
|---|---|---|---|---|---|---|
| ComEd Interconnection Request AE1-172 (Wind) | Wind (onshore) | IL | 8.0 yrs | 255 MW | Interconnection study | System Impact Study |
| ComEd Interconnection Request AE2-261 (Solar) | Solar | IL | 7.4 yrs | 299 MW | Interconnection study | System Impact Study |
| ComEd Interconnection Request AF2-041 (Solar) | Solar | IL | 6.7 yrs | 300 MW | Interconnection study | System Impact Study |
| ComEd Interconnection Request AF2-182 (Solar) | Solar | IL | 6.5 yrs | 300 MW | Interconnection study | Feasibility Study |
| ComEd Interconnection Request AF2-349 (Solar) | Solar | IL | 6.4 yrs | 300 MW | Interconnection study | System Impact Study |
| ComEd Interconnection Request AG1-118 (Solar) | Solar | IL | 6.0 yrs | 300 MW | Interconnection study | Feasibility Study |
| ComEd Interconnection Request AG1-374 (Solar) | Solar | IL | 5.9 yrs | 300 MW | Interconnection study | Feasibility Study |
| ComEd Interconnection Request AG1-553 (Solar) | Solar | IL | 5.9 yrs | 260 MW | Interconnection study | Feasibility Study |
| ComEd Interconnection Request AG1-462 (Solar) | Solar | IL | 5.9 yrs | 255 MW | Interconnection study | Feasibility Study |
| AMEREN ILLINOIS Interconnection Request J2128 (Wind+Battery) | Wind (onshore) | IL | 5.1 yrs | 300 MW | Interconnection study | Cluster Study |
| ComEd Interconnection Request AH2-113 (Solar+Battery) | Solar | IL | 4.5 yrs | 250 MW | Interconnection study | Feasibility Study |
| ComEd Interconnection Request AH2-270 (Wind) | Wind (onshore) | IL | 4.5 yrs | 300 MW | Interconnection study | Feasibility Study |
| ComEd Interconnection Request AH2-340 (Solar) | Solar | IL | 4.5 yrs | 350 MW | Interconnection study | Feasibility Study |
| ComEd Interconnection Request AH2-342 (Solar) | Solar | IL | 4.5 yrs | 280 MW | Interconnection study | Feasibility Study |
| ComEd Interconnection Request AH2-415 (Battery) | Storage | IL | 4.5 yrs | 300 MW | Interconnection study | Feasibility Study |
| ComEd Interconnection Request AH2-416 (Battery) | Storage | IL | 4.5 yrs | 450 MW | Interconnection study | Feasibility Study |
| AMEREN TRANSMISSION COMPANY OF ILLINOIS Interconnection Request J2275 (Wind) | Wind (onshore) | IL | 4.5 yrs | 250 MW | Interconnection study | Cluster Study |
| AMEREN ILLINOIS Interconnection Request J2267 (Solar+Battery) | Solar | IL | 4.5 yrs | 250 MW | Interconnection study | Cluster Study |
| AMEREN ILLINOIS Interconnection Request J2171 (Solar+Wind) | Wind (onshore) | IL | 4.5 yrs | 500 MW | Interconnection study | Cluster Study |
| ComEd Interconnection Request AI1-024 (Battery) | Storage | IL | 4.4 yrs | 300 MW | Interconnection study | Feasibility Study |
| AMEREN TRANSMISSION COMPANY OF ILLINOIS Interconnection Request J2186 (Solar) | Solar | IL | 4.2 yrs | 821 MW | Interconnection study | Cluster Study |
| Grain Belt Express LLC (IL ICC Docket 22-0499) | Transmission | IL | 4.1 yrs | Not disclosed | Local/state review | — |
| GREAT RIVER ENERGY Interconnection Request S1036 (Wind+Other) | Wind (onshore) | IL | 4.0 yrs | 400 MW | Interconnection study | — |
| ComEd Interconnection Request AI1-149 (Battery) | Storage | IL | 4.0 yrs | 250 MW | Interconnection study | Feasibility Study |
| ComEd Interconnection Request AI1-172 (Solar+Battery) | Solar | IL | 4.0 yrs | 250 MW | Interconnection study | Feasibility Study |
| AMEREN TRANSMISSION COMPANY OF ILLINOIS Interconnection Request J3078 (Wind) | Wind (onshore) | IL | 4.0 yrs | 252 MW | Interconnection study | Cluster Study |
| MIDAMERICAN ENERGY CO. Interconnection Request J2556 (Solar) | Solar | IL | 4.0 yrs | 300 MW | Interconnection study | Cluster Study |
| AMEREN ILLINOIS Interconnection Request J2565 (Solar) | Solar | IL | 4.0 yrs | 265 MW | Interconnection study | Cluster Study |
| AMEREN ILLINOIS Interconnection Request J2647 (Battery) | Storage | IL | 4.0 yrs | 300 MW | Interconnection study | Cluster Study |
| AMEREN ILLINOIS Interconnection Request J2793 (Solar) | Solar | IL | 4.0 yrs | 250 MW | Interconnection study | Cluster Study |
| AMEREN ILLINOIS Interconnection Request J2922 (Solar) | Solar | IL | 4.0 yrs | 250 MW | Interconnection study | Cluster Study |
| AMEREN TRANSMISSION COMPANY OF ILLINOIS Interconnection Request J3027 (Wind+Battery) | Wind (onshore) | IL | 4.0 yrs | 300 MW | Interconnection study | Cluster Study |
| AMEREN ILLINOIS Interconnection Request J3015 (Wind+Battery) | Wind (onshore) | IL | 4.0 yrs | 400 MW | Interconnection study | Cluster Study |
| AMEREN ILLINOIS Interconnection Request J3012 (Solar) | Solar | IL | 4.0 yrs | 287 MW | Interconnection study | Cluster Study |
| AMEREN TRANSMISSION COMPANY OF ILLINOIS Interconnection Request J2390 (Solar+Battery) | Solar | IL | 4.0 yrs | 350 MW | Interconnection study | Cluster Study |
| AMEREN ILLINOIS Interconnection Request J2603 (Solar) | Solar | IL | 4.0 yrs | 320 MW | Interconnection study | Cluster Study |
| AMEREN ILLINOIS Interconnection Request J2662 (Solar) | Solar | IL | 4.0 yrs | 250 MW | Interconnection study | Cluster Study |
| AMEREN ILLINOIS Interconnection Request J2690 (Wind+Battery) | Wind (onshore) | IL | 4.0 yrs | 500 MW | Interconnection study | Cluster Study |
| AMEREN ILLINOIS Interconnection Request J2694 (Solar+Wind+Battery) | Wind (onshore) | IL | 4.0 yrs | 500 MW | Interconnection study | Cluster Study |
| AMEREN TRANSMISSION COMPANY OF ILLINOIS Interconnection Request J2973 (Solar) | Solar | IL | 4.0 yrs | 250 MW | Interconnection study | Cluster Study |
| DUKE ENERGY INDIANA Interconnection Request J3076 (Solar+Battery) | Solar | IL | 4.0 yrs | 500 MW | Interconnection study | Cluster Study |
| AMEREN ILLINOIS Interconnection Request J3074 (Solar) | Solar | IL | 4.0 yrs | 250 MW | Interconnection study | Cluster Study |
| AMEREN ILLINOIS Interconnection Request J3216 (Battery) | Storage | IL | 4.0 yrs | 300 MW | Interconnection study | Cluster Study |
| ComEd Interconnection Request AJ1-011 (Battery) | Storage | IL | 3.3 yrs | 328 MW | Interconnection study | Feasibility Study |
| ComEd Interconnection Request AJ1-014 (Battery) | Storage | IL | 3.3 yrs | 260 MW | Interconnection study | Feasibility Study |
| ComEd Interconnection Request AJ1-012 (Battery) | Storage | IL | 3.3 yrs | 354 MW | Interconnection study | Feasibility Study |
| ComEd Interconnection Request AJ1-013 (Battery) | Storage | IL | 3.3 yrs | 250 MW | Interconnection study | Feasibility Study |
| AMEREN ILLINOIS Interconnection Request J3412 (Solar) | Solar | IL | 2.5 yrs | 300 MW | Interconnection study | In Progress (unknown study) |
| AMEREN ILLINOIS Interconnection Request J3805 (Solar) | Solar | IL | 2.4 yrs | 250 MW | Interconnection study | In Progress (unknown study) |
| AMEREN TRANSMISSION COMPANY OF ILLINOIS Interconnection Request J3498 (Solar) | Solar | IL | 2.4 yrs | 300 MW | Interconnection study | In Progress (unknown study) |
| AMEREN ILLINOIS Interconnection Request J3417 (Battery) | Storage | IL | 2.4 yrs | 300 MW | Interconnection study | In Progress (unknown study) |
| MIDAMERICAN ENERGY CO. Interconnection Request J3525 (Battery) | Storage | IL | 2.4 yrs | 300 MW | Interconnection study | In Progress (unknown study) |
| AMEREN ILLINOIS Interconnection Request J3521 (Wind) | Wind (onshore) | IL | 2.4 yrs | 350 MW | Interconnection study | In Progress (unknown study) |
| AMEREN TRANSMISSION COMPANY OF ILLINOIS Interconnection Request J3558 (Battery) | Storage | IL | 2.4 yrs | 300 MW | Interconnection study | In Progress (unknown study) |
| AMEREN TRANSMISSION COMPANY OF ILLINOIS Interconnection Request J3556 (Solar) | Solar | IL | 2.4 yrs | 250 MW | Interconnection study | In Progress (unknown study) |
| AMEREN ILLINOIS Interconnection Request J3681 (Wind) | Wind (onshore) | IL | 2.4 yrs | 300 MW | Interconnection study | In Progress (unknown study) |
| MIDAMERICAN ENERGY CO. Interconnection Request J3699 (Wind) | Wind (onshore) | IL | 2.4 yrs | 300 MW | Interconnection study | In Progress (unknown study) |
| AMEREN TRANSMISSION COMPANY OF ILLINOIS Interconnection Request J3712 (Wind) | Wind (onshore) | IL | 2.4 yrs | 400 MW | Interconnection study | In Progress (unknown study) |
| AMEREN ILLINOIS Interconnection Request J3730 (Wind) | Wind (onshore) | IL | 2.4 yrs | 444 MW | Interconnection study | In Progress (unknown study) |
| MIDAMERICAN ENERGY CO. Interconnection Request J3750 (Wind) | Wind (onshore) | IL | 2.4 yrs | 250 MW | Interconnection study | In Progress (unknown study) |
| AMEREN ILLINOIS Interconnection Request R1055 (Other+Battery) | Storage | IL | 2.2 yrs | 322 MW | Interconnection study | — |
| AMEREN ILLINOIS Interconnection Request S1057 (Solar+Other) | Solar | IL | 2.1 yrs | 360 MW | Interconnection study | — |
| AMEREN ILLINOIS Interconnection Request J2377 (Battery) | Storage | IL | 1.8 yrs | 300 MW | Interconnection study | Cluster Study |
| AMEREN ILLINOIS Interconnection Request J3853 (Wind) | Wind (onshore) | IL | 1.7 yrs | 300 MW | Interconnection study | — |
| AMEREN ILLINOIS Interconnection Request J3901 (Wind) | Wind (onshore) | IL | 1.6 yrs | 300 MW | Interconnection study | — |
| AMEREN ILLINOIS Interconnection Request J3860 (Wind) | Wind (onshore) | IL | 1.6 yrs | 500 MW | Interconnection study | — |
| ComEd Interconnection Request AG2-453 (Solar) | Solar | IL | 1.6 yrs | 280 MW | Interconnection study | System Impact Study |
| AMEREN ILLINOIS Interconnection Request J3883 (Battery) | Storage | IL | 1.6 yrs | 250 MW | Interconnection study | — |
| AMEREN ILLINOIS Interconnection Request J3882 (Solar) | Solar | IL | 1.6 yrs | 250 MW | Interconnection study | — |
| AMEREN ILLINOIS Interconnection Request J3950 (Solar) | Solar | IL | 1.5 yrs | 340 MW | Interconnection study | — |
| ComEd Interconnection Request AG2-363 (Solar) | Solar | IL | 1.5 yrs | 300 MW | Interconnection study | System Impact Study |
| ComEd Interconnection Request AG2-545 (Battery) | Storage | IL | 1.5 yrs | 400 MW | Interconnection study | System Impact Study |
| Interconnection Request J3946 (Battery) | Storage | IL | 1.4 yrs | 300 MW | Interconnection study | — |
| AMEREN TRANSMISSION COMPANY OF ILLINOIS Interconnection Request J3954 (Solar) | Solar | IL | 1.4 yrs | 250 MW | Interconnection study | — |
| Interconnection Request J3991 (Wind) | Wind (onshore) | IL | 1.4 yrs | 340 MW | Interconnection study | — |
| AMEREN TRANSMISSION COMPANY OF ILLINOIS Interconnection Request J4000 (Solar) | Solar | IL | 1.4 yrs | 343 MW | Interconnection study | — |
| AMEREN ILLINOIS Interconnection Request J4018 (Wind) | Wind (onshore) | IL | 1.3 yrs | 250 MW | Interconnection study | — |
| Interconnection Request J4198 (Battery) | Storage | IL | 1.0 yrs | 250 MW | Interconnection study | — |
| Interconnection Request J4118 (Battery) | Storage | IL | 1.0 yrs | 250 MW | Interconnection study | — |
| MIDAMERICAN ENERGY CO. Interconnection Request J4112 (Wind) | Wind (onshore) | IL | 0.9 yrs | 300 MW | Interconnection study | — |
| Commonwealth Edison Company (IL ICC Docket 26-0156) | Transmission | IL | 0.5 yrs | Not disclosed | Local/state review | — |
| Prairie Oak Solar (Unit 11102) | Solar | IL | — | 250 MW | Planned, approvals not yet initiated | — |
| Lincoln Land Energy Center (Unit GEN1) | Gas | IL | — | 638 MW | Planned, approvals not yet initiated | — |
| Lincoln Land Energy Center (Unit GEN2) | Gas | IL | — | 638 MW | Planned, approvals not yet initiated | — |
| G3 Expansion Project | Pipeline | IL | — | Not disclosed | Agency permitting | — |
| Steward Creek Solar Phase 1 (Unit SC1) | Solar | IL | — | Not disclosed | Planned, approvals not yet initiated | — |
| Guardian Pipeline Project (DT Midstream) | Pipeline | WI,IL | — | 537 MMcf/d | Agency permitting | — |
| Midwestern Gas Transmission Expansion (Midwestern Gas Transmission Co. (DT Midstream)) | Pipeline | IL,TN | — | 1,500 MMcf/d | Planned, approvals not yet initiated | — |
| NGPL Gulf Coast Southbound Project (Phase III) (Nat Gas P L Co of America) | Pipeline | IA,IL,MO,AR,TX | — | 260 MMcf/d | Agency permitting | — |
| North Extension Project (Natural Gas Pipeline Company of America LLC) | Pipeline | IA,IL,WI | — | 210 MMcf/d | Agency permitting | — |
| Vector Pipeline Expansion (Vector Pipeline (DT Midstream / Enbridge JV)) | Pipeline | IN,MI,IL | — | 400 MMcf/d | Agency permitting | — |