generation · Solar
AMEREN TRANSMISSION COMPANY OF ILLINOIS Interconnection Request J3556 (Solar)
Montgomery, IL
Capacity
250 MW
Waiting
2.4 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
In Progress (unknown study)
Grid region
MISO
Point of interconnection
7COFFEEN - 7PANA 345.0kV
Queue cluster
DPP-2023 Central
Estimated investment waiting
$331.8M
≈ 250,000 kW × $1,327/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.
Location
39.2281, -89.4781 — see the map for this project in context with others.
Public Hearings
Unknown
Hearing details: Unknown
Not available from this project’s data source yet. Check the sources below directly.
Sources
Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.