generation · Wind (onshore)

GREAT RIVER ENERGY Interconnection Request S1036 (Wind+Other)

Mclean, IL

Capacity
400 MW
Waiting
4.0 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Grid region
MISO
Point of interconnection
Dickinson 345 kV, Buffalo, MN

Estimated investment waiting

$687.2M

400,000 kW × $1,718/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.

Location

40.4946, -88.8445 — see the map for this project in context with others.

Public Hearings

Unknown

Hearing details: Unknown

Not available from this project’s data source yet. Check the sources below directly.

Sources

Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.