WaitingForPower
generation · Wind (onshore)

ComEd Interconnection Request AE1-172 (Wind)

Livingston, IL

Developer: Livingston Wind Project, LLC

Capacity
255 MW
Waiting
8.0 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
System Impact Study
Grid region
PJM
Point of interconnection
Loretto-Wilton Center
Queue cluster
TC1

Estimated investment waiting

$438.1M

255,000 kW × $1,718/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.

Location

40.8944, -88.5529 — see the map for this project in context with others.

Public Hearings

Unknown

Hearing details: Unknown

Not available from this project’s data source yet. Check the sources below directly.

Sources

Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.