Florida energy projects waiting for approval
11 projects currently waiting on a permitting decision in Florida, tracked live from public federal and state sources. See every state →
11
Projects
5,418 MW
Capacity waiting
2,600 MW
Clean energy capacity waiting
2/11 projects are zero-carbon generation
$21.54B
Est. investment waiting
8/11 projects have an applicable estimate
Documented estimates, not precise figures. See methodology.
11 projects
| Project | Fuel | Location | Waiting ↓ | Capacity | Stage | Queue stage |
|---|---|---|---|---|---|---|
| Duke Energy Florida Interconnection Request 4 (Gas) | Gas | FL | 27.4 yrs | 537 MW | Interconnection study | In Progress (unknown study) |
| Florida Power & Light Interconnection Request 108 (Nuclear) | Nuclear | FL | 19.0 yrs | 1,300 MW | Interconnection study | Facility Study |
| Florida Power & Light Interconnection Request 107 (Nuclear) | Nuclear | FL | 19.0 yrs | 1,300 MW | Interconnection study | Facility Study |
| Jacksonville Electric Authority Interconnection Request JEA-Q008 (Gas) | Gas | FL | 8.5 yrs | 645 MW | Interconnection study | Feasibility Study |
| Florida Power & Light Interconnection Request 620 (Battery) | Storage | FL | 2.7 yrs | 400 MW | Interconnection study | System Impact Study |
| Duke Energy Florida Interconnection Request FC100382 (Gas) | Gas | FL | 0.7 yrs | 265 MW | Interconnection study | In Progress (unknown study) |
| Duke Energy Florida Interconnection Request FC100386 (Gas) | Gas | FL | 0.7 yrs | 265 MW | Interconnection study | In Progress (unknown study) |
| Florida Power & Light Company (FPL) (FL Siting Case TA26-21) | Transmission | FL | 0.3 yrs | Not disclosed | Agency permitting | — |
| JEA (FL Siting Case PA81-13A2) | Gas | FL | 0.3 yrs | 706 MW | Agency permitting | — |
| Florida Gas Transmission Phase 9 Expansion (Florida Gas Transmission (Energy Transfer)) | Pipeline | FL | — | 550 MMcf/d | Planned, approvals not yet initiated | — |
| South Florida Reliability Project (Florida Gas Transmission (Energy Transfer)) | Pipeline | FL | — | Not disclosed | Planned, approvals not yet initiated | — |