Washington energy projects waiting for approval

67 projects currently waiting on a permitting decision in Washington, tracked live from public federal and state sources. See every state →

67
Projects
28,411 MW
Capacity waiting
22,525 MW
Clean energy capacity waiting
53/67 projects are zero-carbon generation
$50.00B
Est. investment waiting
65/67 projects have an applicable estimate
Documented estimates, not precise figures. See methodology.
67 projects
Project Fuel Location Waiting Capacity Stage Queue stage
Interconnection Request G0490 (Hydro)HydroWA13.2 yrs345 MWInterconnection studyFacility Study
Interconnection Request G0558 (Wind)Wind (onshore)WA9.5 yrs500 MWInterconnection studyFacility Study
Interconnection Request G0559 (Wind)Wind (onshore)WA9.5 yrs250 MWInterconnection studyFacility Study
Interconnection Request G0585 (Wind)Wind (onshore)WA8.5 yrs313 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G0589 (Solar)SolarWA8.3 yrs381 MWInterconnection studyFacility Study
Interconnection Request G0608 (Battery)StorageWA7.8 yrs1,200 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G0656 (Battery)StorageWA6.0 yrs500 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G0668 (Solar+Battery)SolarWA5.6 yrs400 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G0670 (Solar+Battery)SolarWA5.5 yrs500 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G0684 (Solar+Battery)SolarWA5.1 yrs470 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G0688 (Solar+Battery)SolarWA5.0 yrs500 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G0760 (Gas+Battery)StorageWA4.2 yrs400 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G0761 (Wind)Wind (onshore)WA4.2 yrs290 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G0822 (Solar+Battery)SolarWA3.8 yrs2,000 MWInterconnection studyIn Progress (unknown study)
Hop Hill Solar (WA EFSEC)SolarWA3.8 yrs500 MWLocal/state review
Carriger Solar (WA EFSEC)SolarWA3.6 yrs160 MWLocal/state review
Interconnection Request G0840 (Solar+Battery)SolarWA3.6 yrs300 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G0844 (Solar+Battery)SolarWA3.5 yrs280 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G0853 (Solar+Battery)SolarWA3.5 yrs300 MWInterconnection studyIn Progress (unknown study)
SKAGIT RIVER (FERC No. P-553)HydroWA3.4 yrs700 MWAgency permitting
Interconnection Request G0872 (Wind)Wind (onshore)WA3.2 yrs300 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G0914 (Battery)StorageWA3.1 yrs1,000 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G0915 (Battery)StorageWA3.1 yrs500 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G0916 (Battery)StorageWA3.1 yrs500 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G0919 (Nuclear)NuclearWA3.0 yrs270 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G0920 (Solar+Battery)SolarWA3.0 yrs500 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G0921 (Wind+Battery)Wind (onshore)WA3.0 yrs357 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G0932 (Solar+Battery)SolarWA3.0 yrs400 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G0933 (Solar+Battery)SolarWA3.0 yrs400 MWInterconnection studyIn Progress (unknown study)
Grant County Public Utility District Interconnection Request 9 (Solar+Battery)SolarWA3.0 yrs300 MWInterconnection studySystem Impact Study
Grant County Public Utility District Interconnection Request 10 (Solar+Battery)SolarWA2.9 yrs300 MWInterconnection studySystem Impact Study
Interconnection Request G0953 (Wind)Wind (onshore)WA2.9 yrs600 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G0954 (Wind)Wind (onshore)WA2.9 yrs350 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G0955 (Wind)Wind (onshore)WA2.9 yrs350 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G0973 (Wind)Wind (onshore)WA2.9 yrs300 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G0998 (Nuclear)NuclearWA2.8 yrs1,120 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G1008 (Gas)GasWA2.8 yrs286 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G1007 (Wind+Battery)Wind (onshore)WA2.8 yrs300 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G1032 (Solar)SolarWA2.8 yrs500 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G1016 (Solar)SolarWA2.8 yrs400 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G1014 (Battery)StorageWA2.8 yrs250 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G1035 (Solar)SolarWA2.8 yrs400 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G1031 (Solar)SolarWA2.8 yrs250 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G1015 (Solar)SolarWA2.8 yrs500 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G1025 (Solar+Wind+Battery)Wind (onshore)WA2.8 yrs509 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G1037 (Solar+Battery)SolarWA2.8 yrs400 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G1038 (Solar+Battery)SolarWA2.8 yrs400 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G1039 (Solar+Battery)SolarWA2.8 yrs400 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G1040 (Solar+Battery)SolarWA2.8 yrs400 MWInterconnection studyIn Progress (unknown study)
Rock Island (FERC No. P-943)HydroWA2.7 yrs395 MWAgency permitting
Wallula Gap Solar (WA EFSEC)SolarWA2.6 yrs60 MWLocal/state review
Puget Sound Energy Interconnection Request 141 (Solar+Wind+Battery)Wind (onshore)WA2.6 yrs300 MWInterconnection studyCluster Study
Goldeneye Battery Storage (WA EFSEC)StorageWA2.3 yrs200 MWLocal/state review
Avista Utilities Interconnection Request CS25-09 (Solar+Battery)SolarWA1.4 yrs375 MWInterconnection studyCluster Study
Avista Utilities Interconnection Request CS25-11 (Wind)Wind (onshore)WA1.4 yrs300 MWInterconnection studyCluster Study
Avista Utilities Interconnection Request CS25-08 (Battery)StorageWA1.4 yrs250 MWInterconnection studyCluster Study
Interconnection Request G1082 (Solar+Battery)SolarWA1.1 yrs400 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G1083 (Solar+Battery)SolarWA1.1 yrs400 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G1080 (Solar+Battery)SolarWA1.1 yrs400 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G1081 (Solar+Battery)SolarWA1.1 yrs400 MWInterconnection studyIn Progress (unknown study)
Interconnection Request G1087 (Solar+Battery)SolarWA0.8 yrs500 MWInterconnection studyIn Progress (unknown study)
Lower Snake Solar Generation BESS (Unit LOSN1)SolarWA300 MWRegulatory approvals pending
Lower Snake Solar Generation BESS (Unit LOSN2)StorageWA300 MWRegulatory approvals pending
Hop Hill Solar Generation and BESS (Unit HOHI1)SolarWA500 MWRegulatory approvals pending
Hop Hill Solar Generation and BESS (Unit HOHI2)StorageWA500 MWRegulatory approvals pending
Royal Slope Power Transmission Line ProjectTransmissionWANot disclosedAgency permitting
Huntingdon Connector (Northwest Pipeline, LLC)PipelineWA87 MMcf/dAgency permitting