Nebraska energy projects waiting for approval
22 projects currently waiting on a permitting decision in Nebraska, tracked live from public federal and state sources. See every state →
22
Projects
6,746 MW
Capacity waiting
1,670 MW
Clean energy capacity waiting
6/22 projects are zero-carbon generation
$8.12B
Est. investment waiting
21/22 projects have an applicable estimate
Documented estimates, not precise figures. See methodology.
22 projects
| Project | Fuel | Location | Waiting ↓ | Capacity | Stage | Queue stage |
|---|---|---|---|---|---|---|
| NPPD Interconnection Request GEN-2020-011 (Solar+Battery) | Solar | NE | 6.4 yrs | 320 MW | Interconnection study | Facility Study |
| NPPD Interconnection Request GEN-2021-057 (Wind) | Wind (onshore) | NE | 5.4 yrs | 300 MW | Interconnection study | Facility Study |
| OPPD Interconnection Request GEN-2023-078 (Gas) | Gas | NE | 2.9 yrs | 255 MW | Interconnection study | Facility Study |
| OPPD Interconnection Request GEN-2023-077 (Gas) | Gas | NE | 2.9 yrs | 255 MW | Interconnection study | Facility Study |
| NPPD Interconnection Request GEN-2023-199 (Solar+Battery) | Solar | NE | 2.9 yrs | 250 MW | Interconnection study | Facility Study |
| OPPD Interconnection Request GEN-2023-079 (Gas) | Gas | NE | 2.9 yrs | 273 MW | Interconnection study | Facility Study |
| NPPD Interconnection Request GEN-2023-224 (Gas) | Gas | NE | 2.9 yrs | 478 MW | Interconnection study | Facility Study |
| NPPD Interconnection Request GEN-2023-222 (Gas) | Gas | NE | 2.9 yrs | 478 MW | Interconnection study | Facility Study |
| NPPD Interconnection Request GEN-2024-021 (Gas) | Gas | NE | 1.9 yrs | 540 MW | Interconnection study | System Impact Study |
| NPPD Interconnection Request GEN-2024-022 (Gas) | Gas | NE | 1.9 yrs | 390 MW | Interconnection study | System Impact Study |
| NPPD Interconnection Request GEN-2024-023 (Gas) | Gas | NE | 1.9 yrs | 270 MW | Interconnection study | System Impact Study |
| OPPD Interconnection Request GEN-2024-038 (Solar) | Solar | NE | 1.9 yrs | 300 MW | Interconnection study | System Impact Study |
| NPPD Interconnection Request GEN-2024-020 (Gas) | Gas | NE | 1.9 yrs | 390 MW | Interconnection study | System Impact Study |
| OPPD Interconnection Request GEN-2024-039 (Solar) | Solar | NE | 1.9 yrs | 250 MW | Interconnection study | System Impact Study |
| NPPD Interconnection Request GEN-2024-140 (Solar) | Solar | NE | 1.5 yrs | 250 MW | Interconnection study | System Impact Study |
| OPPD Interconnection Request GEN-2024-212 (Gas) | Gas | NE | 1.5 yrs | 303 MW | Interconnection study | System Impact Study |
| OPPD Interconnection Request GEN-2024-213 (Gas) | Gas | NE | 1.5 yrs | 360 MW | Interconnection study | System Impact Study |
| OPPD Interconnection Request GEN-2024-211 (Gas) | Gas | NE | 1.5 yrs | 303 MW | Interconnection study | System Impact Study |
| OPPD Interconnection Request GEN-2024-372 (Battery) | Storage | NE | 1.5 yrs | 250 MW | Interconnection study | System Impact Study |
| Princeton Road Station (Unit CT1) | Gas | NE | — | 265 MW | Planned, approvals not yet initiated | — |
| Princeton Road Station (Unit CT2) | Gas | NE | — | 265 MW | Planned, approvals not yet initiated | — |
| Central Mainline Corridor Expansion (Northern Natural Gas Co. (Berkshire Hathaway Energy)) | Pipeline | NE,IA | — | 535 MMcf/d | Agency permitting | — |