Capacity
255 MW
Waiting
2.9 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
Facility Study
Grid region
SPP
Point of interconnection
Substation 3740 345 kV
Queue cluster
DISIS-2023-001; 02 NEBRASKA
Estimated investment waiting
$288.1M
≈ 255,000 kW × $1,130/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.
Location
40.9099, -96.1406 — see the map for this project in context with others.
Public Hearings
Unknown
Hearing details: Unknown
Not available from this project’s data source yet. Check the sources below directly.
Sources
Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.