Kansas energy projects waiting for approval

39 projects currently waiting on a permitting decision in Kansas, tracked live from public federal and state sources. See every state →

39
Projects
14,104 MW
Capacity waiting
8,730 MW
Clean energy capacity waiting
26/39 projects are zero-carbon generation
$19.29B
Est. investment waiting
37/39 projects have an applicable estimate
Documented estimates, not precise figures. See methodology.
39 projects
Project Fuel Location Waiting Capacity Stage Queue stage
SUNC Interconnection Request GEN-2021-070 (Wind)Wind (onshore)KS5.4 yrs504 MWInterconnection studyFacility Study
WERE Interconnection Request GEN-2021-096 (Solar)SolarKS5.4 yrs500 MWInterconnection studyFacility Study
WERE Interconnection Request GEN-2021-006 (Battery)StorageKS5.3 yrs300 MWInterconnection studyFacility Study
KCPL Interconnection Request GEN-2021-030 (Solar)SolarKS5.3 yrs510 MWInterconnection studyFacility Study
KCPL Interconnection Request GEN-2021-029 (Battery)StorageKS5.3 yrs254 MWInterconnection studyFacility Study
SUNC Interconnection Request GEN-2022-015 (Solar)SolarKS4.2 yrs270 MWInterconnection studyFacility Study
WERE Interconnection Request GEN-2022-013 (Solar)SolarKS4.2 yrs300 MWInterconnection studyFacility Study
WERE Interconnection Request GEN-2022-161 (Wind)Wind (onshore)KS3.5 yrs360 MWInterconnection studyFacility Study
SPS Interconnection Request GEN-2023-015 (Solar)SolarKS2.9 yrs330 MWInterconnection studyFacility Study
WERE Interconnection Request GEN-2023-099 (Solar)SolarKS2.9 yrs300 MWInterconnection studyFacility Study
SUNC Interconnection Request GEN-2023-107 (Wind)Wind (onshore)KS2.9 yrs300 MWInterconnection studyFacility Study
WERE Interconnection Request GEN-2023-221 (Solar)SolarKS2.9 yrs250 MWInterconnection studyFacility Study
WERE Interconnection Request GEN-2023-220 (Solar)SolarKS2.9 yrs250 MWInterconnection studyFacility Study
ITCGP Interconnection Request GEN-2024-016 (Wind)Wind (onshore)KS1.9 yrs300 MWInterconnection studySystem Impact Study
SUNC Interconnection Request GEN-2024-032 (Solar)SolarKS1.9 yrs250 MWInterconnection studySystem Impact Study
ITCGP Interconnection Request GEN-2024-067 (Solar)SolarKS1.9 yrs380 MWInterconnection studySystem Impact Study
SUNC Interconnection Request GEN-2024-102 (Wind)Wind (onshore)KS1.5 yrs401 MWInterconnection studySystem Impact Study
WERE Interconnection Request GEN-2024-125 (Solar)SolarKS1.5 yrs400 MWInterconnection studySystem Impact Study
WERE Interconnection Request GEN-2024-129 (Gas)GasKS1.5 yrs910 MWInterconnection studySystem Impact Study
NEETSW Interconnection Request GEN-2024-139 (Solar)SolarKS1.5 yrs250 MWInterconnection studySystem Impact Study
WERE Interconnection Request GEN-2024-142 (Wind)Wind (onshore)KS1.5 yrs300 MWInterconnection studySystem Impact Study
WERE Interconnection Request GEN-2024-166 (Solar+Battery)SolarKS1.5 yrs275 MWInterconnection studySystem Impact Study
WERE Interconnection Request GEN-2024-176 (Battery)StorageKS1.5 yrs250 MWInterconnection studySystem Impact Study
SUNC Interconnection Request GEN-2024-144 (Wind)Wind (onshore)KS1.5 yrs300 MWInterconnection studySystem Impact Study
SUNC Interconnection Request GEN-2024-137 (Wind)Wind (onshore)KS1.5 yrs300 MWInterconnection studySystem Impact Study
SUNC Interconnection Request GEN-2024-138 (Wind)Wind (onshore)KS1.5 yrs300 MWInterconnection studySystem Impact Study
SUNC Interconnection Request GEN-2024-136 (Solar)SolarKS1.5 yrs400 MWInterconnection studySystem Impact Study
WERE Interconnection Request GEN-2024-249 (Gas)GasKS1.5 yrs721 MWInterconnection studySystem Impact Study
WERE Interconnection Request GEN-2024-253 (Gas+Battery)StorageKS1.5 yrs300 MWInterconnection studySystem Impact Study
NEETSW Interconnection Request GEN-2024-258 (Wind)Wind (onshore)KS1.5 yrs300 MWInterconnection studySystem Impact Study
ITCGP Interconnection Request GEN-2024-215 (Solar+Battery)SolarKS1.5 yrs300 MWInterconnection studySystem Impact Study
WERE Interconnection Request GEN-2024-339 (Battery)StorageKS1.5 yrs300 MWInterconnection studySystem Impact Study
WERE Interconnection Request GEN-2025-SR16 (Battery)StorageKS1.3 yrs300 MWInterconnection studyFacility Study
SEPC Interconnection Request ERAS-2025-017 (Gas)GasKS1.0 yrs600 MWInterconnection studyIn Progress (unknown study)
SEPC Interconnection Request ERAS-2025-015 (Solar+Battery)SolarKS1.0 yrs400 MWInterconnection studyIn Progress (unknown study)
WERE Interconnection Request ERAS-2025-006 (Gas)GasKS0.9 yrs718 MWInterconnection studyIn Progress (unknown study)
WERE Interconnection Request ERAS-2025-008 (Gas)GasKS0.9 yrs721 MWInterconnection studyIn Progress (unknown study)
Midwest Market Access Project (Southern Star Central Gas Pipeline)PipelineOK,KS160 MMcf/dAgency permitting
Viola Project (Southern Star Central Gas Pipeline)PipelineKS116 MMcf/dAgency permitting