generation · Gas

WERE Interconnection Request ERAS-2025-006 (Gas)

Reno, KS

Capacity
718 MW
Waiting
0.9 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
In Progress (unknown study)
Grid region
SPP
Point of interconnection
Reno County 345 kV Substation #1443
Queue cluster
ERAS-2025-001; 03 CENTRAL

Estimated investment waiting

$811.1M

717,800 kW × $1,130/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.

Location

37.9482, -98.0783 — see the map for this project in context with others.

Public Hearings

Unknown

Hearing details: Unknown

Not available from this project’s data source yet. Check the sources below directly.

Sources

Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.