Idaho energy projects waiting for approval
18 projects currently waiting on a permitting decision in Idaho, tracked live from public federal and state sources. See every state →
18
Projects
5,477 MW
Capacity waiting
3,695 MW
Clean energy capacity waiting
9/18 projects are zero-carbon generation
$9.95B
Est. investment waiting
13/18 projects have an applicable estimate
Documented estimates, not precise figures. See methodology.
18 projects
| Project | Fuel | Location | Waiting ↓ | Capacity | Stage | Queue stage |
|---|---|---|---|---|---|---|
| HELLS CANYON (FERC No. P-1971) | Hydro | ID | 23.1 yrs | 1,167 MW | Agency permitting | — |
| BPA Power Services Interconnection Request G0492 (Hydro) | Hydro | ID | 13.1 yrs | 300 MW | Interconnection study | Facility Study |
| Idaho Power Company Interconnection Request 737 (Solar) | Solar | ID | 3.0 yrs | 280 MW | Interconnection study | Cluster Study |
| Interconnection Request G0956 (Wind) | Wind (onshore) | ID | 2.9 yrs | 400 MW | Interconnection study | In Progress (unknown study) |
| Idaho Power Company Interconnection Request 763 (Wind) | Wind (onshore) | ID | 1.4 yrs | 300 MW | Interconnection study | Cluster Study |
| Idaho Power Company Interconnection Request 772 (Solar+Battery) | Solar | ID | 1.4 yrs | 300 MW | Interconnection study | Cluster Study |
| Idaho Power Company Interconnection Request 759 (Gas) | Gas | ID | 1.4 yrs | 526 MW | Interconnection study | Cluster Study |
| Idaho Power Company Interconnection Request 760 (Gas) | Gas | ID | 1.4 yrs | 526 MW | Interconnection study | Cluster Study |
| Idaho Power Company Interconnection Request 792 (Battery) | Storage | ID | 1.4 yrs | 330 MW | Interconnection study | Cluster Study |
| Idaho Power Company Interconnection Request 793 (Solar+Battery) | Solar | ID | 1.4 yrs | 250 MW | Interconnection study | Cluster Study |
| PacifiCorp Interconnection Request T2-029 (Solar+Battery) | Solar | ID | 1.0 yrs | 398 MW | Interconnection study | — |
| PacifiCorp Interconnection Request T2-025 (Wind) | Wind (onshore) | ID | 1.0 yrs | 300 MW | Interconnection study | — |
| PacifiCorp Interconnection Request T2-040 (Gas) | Gas | ID | 1.0 yrs | 400 MW | Interconnection study | — |
| IDAHO POWER COMPANY (Idaho PUC Case IPC-E-26-04) | Other | ID | 0.5 yrs | Not disclosed | Local/state review | — |
| PACIFICORP DBA ROCKY MOUNTAIN POWER (Idaho PUC Case PAC-E-26-06) | Transmission | ID | 0.4 yrs | Not disclosed | Local/state review | — |
| IDAHO POWER COMPANY (Idaho PUC Case IPC-E-26-09) | Transmission | ID | 0.4 yrs | Not disclosed | Local/state review | — |
| AVISTA UTILITIES, INC (Idaho PUC Case AVU-E-26-10) | Transmission | ID | 0.2 yrs | Not disclosed | Local/state review | — |
| Crow Creek Pipeline Project | Pipeline | ID | — | Not disclosed | Agency permitting | — |