| ENTERGY ARKANSAS Interconnection Request J2477 (Solar) | Solar | AR | 4.0 yrs | 600 MW | Interconnection study | Cluster Study |
| ENTERGY ARKANSAS Interconnection Request J2864 (Solar) | Solar | AR | 4.0 yrs | 375 MW | Interconnection study | Cluster Study |
| ENTERGY ARKANSAS Interconnection Request J2866 (Solar) | Solar | AR | 4.0 yrs | 375 MW | Interconnection study | Cluster Study |
| ENTERGY ARKANSAS Interconnection Request J2865 (Solar) | Solar | AR | 4.0 yrs | 375 MW | Interconnection study | Cluster Study |
| ENTERGY ARKANSAS Interconnection Request J3040 (Solar) | Solar | AR | 4.0 yrs | 365 MW | Interconnection study | Cluster Study |
| ENTERGY ARKANSAS Interconnection Request J2395 (Solar) | Solar | AR | 4.0 yrs | 500 MW | Interconnection study | Cluster Study |
| ENTERGY ARKANSAS Interconnection Request J2478 (Solar) | Solar | AR | 4.0 yrs | 550 MW | Interconnection study | Cluster Study |
| ENTERGY ARKANSAS Interconnection Request J2482 (Solar) | Solar | AR | 4.0 yrs | 300 MW | Interconnection study | Cluster Study |
| ENTERGY ARKANSAS Interconnection Request J2523 (Solar) | Solar | AR | 4.0 yrs | 250 MW | Interconnection study | Cluster Study |
| ENTERGY ARKANSAS Interconnection Request J3030 (Solar+Battery) | Solar | AR | 4.0 yrs | 450 MW | Interconnection study | Cluster Study |
| ENTERGY ARKANSAS Interconnection Request J3131 (Solar) | Solar | AR | 4.0 yrs | 300 MW | Interconnection study | Cluster Study |
| ENTERGY ARKANSAS Interconnection Request J2396 (Solar) | Solar | AR | 4.0 yrs | 400 MW | Interconnection study | Cluster Study |
| ENTERGY ARKANSAS Interconnection Request J2613 (Wind) | Wind (onshore) | AR | 4.0 yrs | 300 MW | Interconnection study | Cluster Study |
| ENTERGY ARKANSAS Interconnection Request J2696 (Solar) | Solar | AR | 4.0 yrs | 500 MW | Interconnection study | Cluster Study |
| ENTERGY ARKANSAS Interconnection Request J2841 (Wind) | Wind (onshore) | AR | 4.0 yrs | 500 MW | Interconnection study | Cluster Study |
| ENTERGY ARKANSAS Interconnection Request J2907 (Solar+Battery) | Solar | AR | 4.0 yrs | 400 MW | Interconnection study | Cluster Study |
| ENTERGY ARKANSAS Interconnection Request J3192 (Solar) | Solar | AR | 4.0 yrs | 500 MW | Interconnection study | Cluster Study |
| ENTERGY ARKANSAS Interconnection Request J3829 (Gas) | Gas | AR | 2.4 yrs | 770 MW | Interconnection study | In Progress (unknown study) |
| ENTERGY ARKANSAS Interconnection Request J3401 (Solar) | Solar | AR | 2.4 yrs | 500 MW | Interconnection study | In Progress (unknown study) |
| ENTERGY ARKANSAS Interconnection Request J3597 (Wind) | Wind (onshore) | AR | 2.4 yrs | 348 MW | Interconnection study | In Progress (unknown study) |
| ENTERGY ARKANSAS Interconnection Request J3874 (Gas) | Gas | AR | 1.7 yrs | 770 MW | Interconnection study | — |
| ENTERGY ARKANSAS Interconnection Request J3982 (Wind) | Wind (onshore) | AR | 1.7 yrs | 320 MW | Interconnection study | — |
| ENTERGY ARKANSAS Interconnection Request J3889 (Solar) | Solar | AR | 1.6 yrs | 350 MW | Interconnection study | — |
| AEP Interconnection Request GEN-2024-226 (Solar) | Solar | AR | 1.5 yrs | 300 MW | Interconnection study | System Impact Study |
| ENTERGY ARKANSAS Interconnection Request J4012 (Solar+Battery) | Solar | AR | 1.3 yrs | 300 MW | Interconnection study | — |
| ENTERGY ARKANSAS Interconnection Request S1105 (Other+Battery) | Storage | AR | 1.2 yrs | 300 MW | Interconnection study | — |
| ENTERGY ARKANSAS Interconnection Request J4074 (Solar) | Solar | AR | 0.9 yrs | 300 MW | Interconnection study | — |
| ENTERGY ARKANSAS Interconnection Request J4196 (Solar) | Solar | AR | 0.9 yrs | 300 MW | Interconnection study | — |
| ENTERGY ARKANSAS Interconnection Request J4088 (Solar+Battery) | Solar | AR | 0.9 yrs | 340 MW | Interconnection study | — |
| ENTERGY ARKANSAS Interconnection Request J4080 (Solar) | Solar | AR | 0.9 yrs | 250 MW | Interconnection study | — |
| ENTERGY ARKANSAS Interconnection Request J4082 (Battery) | Storage | AR | 0.9 yrs | 500 MW | Interconnection study | — |
| ENTERGY ARKANSAS Interconnection Request S1125 (Solar+Battery) | Solar | AR | 0.9 yrs | 400 MW | Interconnection study | — |
| Entergy Arkansas, LLC (AR PSC Docket 26-002-U) | Transmission | AR | 0.6 yrs | Not disclosed | Local/state review | — |
| Entergy Arkansas, LLC (AR PSC Docket 26-041-U) | Transmission | AR | 0.3 yrs | Not disclosed | Local/state review | — |
| Ironwood Power Station (Unit 1A) | Gas | AR | — | 467 MW | Regulatory approvals pending | — |
| Arkansas Cypress Solar Station (Unit PB1) | Solar | AR | — | 600 MW | Planned, approvals not yet initiated | — |
| Arkansas Cypress Solar Station (Unit PB2) | Storage | AR | — | 350 MW | Planned, approvals not yet initiated | — |
| Jefferson Power Station (Unit JPS1) | Gas | AR | — | 342 MW | Regulatory approvals pending | — |
| Jefferson Power Station (Unit JPSCT) | Gas | AR | — | 478 MW | Regulatory approvals pending | — |
| NGPL Gulf Coast Southbound Project (Phase III) (Nat Gas P L Co of America) | Pipeline | IA,IL,MO,AR,TX | — | 260 MMcf/d | Agency permitting | — |
| Texas-Arkansas Power Project (TAPP) (Kinder Morgan (NGPL)) | Pipeline | TX,AR | — | 400 MMcf/d | Agency permitting | — |