WaitingForPower
generation · Gas

Mullin Creek #1 Generating Station (Unit MC1)

Nodaway, MO

Developer: Evergy Missouri West (Electric Utility)

Capacity
490 MW
Waiting
Stage
Approved, awaiting construction
Verification
Verified (primary source)
Grid region
SWPP
Equipment
Combustion (gas) turbine
Expected online
Jan 2030*

* Approximate / developer-estimated date, not a firm commitment.

Estimated investment waiting

$553.4M

489,700 kW × $1,130/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.

Location

38.0059, -97.9217 — see the map for this project in context with others.

Public Hearings

Unknown

Hearing details: Unknown

Not available from this project’s data source yet. Check the sources below directly.

Sources

Data quality note: No application-filed date is published by EIA-860M, so days/years waiting cannot be computed until one is added via manual override — only a planned operation date (1/2030) is available.