West Virginia energy projects waiting for approval
7 projects currently waiting on a permitting decision in West Virginia, tracked live from public federal and state sources. See every state →
7
Projects
3,672 MW
Capacity waiting
0 MW
Clean energy capacity waiting
0/7 projects are zero-carbon generation
$4.15B
Est. investment waiting
3/7 projects have an applicable estimate
Documented estimates, not precise figures. See methodology.
7 projects
| Project | Fuel | Location | Waiting ↓ | Capacity | Stage | Queue stage |
|---|---|---|---|---|---|---|
| APS Interconnection Request AG2-582 (Gas) | Gas | WV | 1.5 yrs | 2,100 MW | Interconnection study | System Impact Study |
| NextEra Energy Transmission MidAtlantic, Inc. (WV PSC Case 26-0075-E-CN) | Transmission | WV | 0.6 yrs | Not disclosed | Local/state review | — |
| Monongahela Power Company and The Potomac Edison Company (WV PSC Case 26-0108-E-CN) | Gas | WV | 0.6 yrs | 1,200 MW | Local/state review | — |
| The Potomac Edison Company (WV PSC Case 26-0135-E-CN-PW) | Transmission | WV | 0.5 yrs | Not disclosed | Local/state review | — |
| Wolf Summit Energy (Unit HCCT1) | Gas | WV | — | 372 MW | Regulatory approvals pending | — |
| Robert C. Byrd Hydroelectric Project | Hydro | WV | — | Not disclosed | Agency permitting | — |
| MVP Boost Expansion (Mountain Valley Pipeline, LLC) | Pipeline | WV,VA | — | 600 MMcf/d | Agency permitting | — |