11 projects currently waiting on a permitting decision in South Dakota, tracked live from public federal and state sources. See every state →

11
Projects
3,709 MW
Capacity waiting
1,800 MW
Clean energy capacity waiting
5/11 projects are zero-carbon generation
$4.85B
Est. investment waiting
9/11 projects have an applicable estimate
Documented estimates, not precise figures. See methodology.
11 projects
Project Fuel Location Waiting Capacity Stage Queue stage
OTTER TAIL POWER COMPANY Interconnection Request J3468 (Wind+Battery)Wind (onshore)SD2.4 yrs300 MWInterconnection studyIn Progress (unknown study)
BEPC Interconnection Request GEN-2024-035 (Solar+Battery)SolarSD1.9 yrs270 MWInterconnection studySystem Impact Study
BEPC Interconnection Request GEN-2024-285 (Wind)Wind (onshore)SD1.5 yrs250 MWInterconnection studySystem Impact Study
OTTER TAIL POWER COMPANY Interconnection Request J3941 (Gas)GasSD1.5 yrs1,144 MWInterconnection study
NORTHERN STATES POWER COMPANY Interconnection Request J3964 (Solar)SolarSD1.4 yrs490 MWInterconnection study
NORTHERN STATES POWER COMPANY Interconnection Request J3963 (Solar)SolarSD1.4 yrs490 MWInterconnection study
Western Minnesota Municipal Power Agency and Missouri River Energy Services (SD PUC EL25-028)TransmissionSD1.1 yrsNot disclosedLocal/state review
Basin Electric Power Cooperative Interconnection Request E0034 (Gas)GasSD1.1 yrs265 MWInterconnection studyIn Progress (unknown study)
OTTER TAIL POWER COMPANY Interconnection Request J4081 (Battery)StorageSD0.9 yrs250 MWInterconnection study
OTTER TAIL POWER COMPANY Interconnection Request J4153 (Battery)StorageSD0.9 yrs250 MWInterconnection study
Crowned Ridge Energy Storage I, LLC (SD PUC EL26-014)StorageSD0.3 yrsNot disclosedLocal/state review