North Carolina energy projects waiting for approval
18 projects currently waiting on a permitting decision in North Carolina, tracked live from public federal and state sources. See every state →
18
Projects
10,300 MW
Capacity waiting
275 MW
Clean energy capacity waiting
1/18 projects are zero-carbon generation
$10.85B
Est. investment waiting
14/18 projects have an applicable estimate
Documented estimates, not precise figures. See methodology.
18 projects
| Project | Fuel | Location | Waiting ↓ | Capacity | Stage | Queue stage |
|---|---|---|---|---|---|---|
| Arizona Public Service Interconnection Request Q362 (Solar+Battery) | Solar | NC | 5.9 yrs | 275 MW | Interconnection study | Cluster Study |
| Duke Energy Progress Interconnection Request 958347 (Gas) | Gas | NC | 2.2 yrs | 1,455 MW | Interconnection study | Cluster Study |
| Duke Energy Carolinas Interconnection Request 960889 (Gas) | Gas | NC | 2.2 yrs | 455 MW | Interconnection study | Cluster Study |
| Duke Energy Carolinas Interconnection Request 961188 (Gas) | Gas | NC | 2.2 yrs | 455 MW | Interconnection study | Cluster Study |
| Duke Energy Carolinas Interconnection Request 961210 (Gas) | Gas | NC | 2.2 yrs | 455 MW | Interconnection study | Cluster Study |
| Duke Energy Progress Interconnection Request PP00027 (Battery) | Storage | NC | 1.4 yrs | 260 MW | Interconnection study | In Progress (unknown study) |
| Duke Energy Carolinas Interconnection Request 977286 (Battery) | Storage | NC | 1.2 yrs | 250 MW | Interconnection study | Cluster Study |
| Duke Energy Carolinas Interconnection Request 977301 (Battery) | Storage | NC | 1.2 yrs | 250 MW | Interconnection study | Cluster Study |
| Duke Energy Progress Interconnection Request 977298 (Other) | Other | NC | 1.2 yrs | 300 MW | Interconnection study | Cluster Study |
| Duke Energy Carolinas Interconnection Request 977564 (Gas) | Gas | NC | 1.2 yrs | 810 MW | Interconnection study | Cluster Study |
| Duke Energy Progress Interconnection Request 977444 (Gas) | Gas | NC | 1.2 yrs | 495 MW | Interconnection study | Cluster Study |
| Duke Energy Progress Interconnection Request 977454 (Gas) | Gas | NC | 1.2 yrs | 990 MW | Interconnection study | Cluster Study |
| Duke Energy Carolinas Interconnection Request 977731 (Gas) | Gas | NC | 1.2 yrs | 1,395 MW | Interconnection study | Cluster Study |
| Duke Energy Progress Interconnection Request 977773 (Gas) | Gas | NC | 1.2 yrs | 260 MW | Interconnection study | Cluster Study |
| Duke Energy Carolinas Interconnection Request 977726 (Gas) | Gas | NC | 1.2 yrs | 1,620 MW | Interconnection study | Cluster Study |
| Duke Energy Progress Interconnection Request PP00041 (Other) | Other | NC | 1.1 yrs | 300 MW | Interconnection study | In Progress (unknown study) |
| Duke Energy Progress Interconnection Request PP00046 (Other) | Other | NC | 1.1 yrs | 275 MW | Interconnection study | In Progress (unknown study) |
| Kitty Hawk South Offshore Wind Project | Wind (offshore) | NC | — | Not disclosed | Agency permitting | — |