Mississippi energy projects waiting for approval
15 projects currently waiting on a permitting decision in Mississippi, tracked live from public federal and state sources. See every state →
15
Projects
4,679 MW
Capacity waiting
1,600 MW
Clean energy capacity waiting
5/15 projects are zero-carbon generation
$5.74B
Est. investment waiting
10/15 projects have an applicable estimate
Documented estimates, not precise figures. See methodology.
15 projects
| Project | Fuel | Location | Waiting ↓ | Capacity | Stage | Queue stage |
|---|---|---|---|---|---|---|
| ENTERGY MISSISSIPPI, LLC. Interconnection Request J2966 (Solar) | Solar | MS | 4.0 yrs | 450 MW | Interconnection study | Cluster Study |
| ENTERGY MISSISSIPPI, LLC. Interconnection Request J2602 (Solar) | Solar | MS | 4.0 yrs | 250 MW | Interconnection study | Cluster Study |
| COOPERATIVE ENERGY Interconnection Request J2999 (Solar) | Solar | MS | 4.0 yrs | 250 MW | Interconnection study | Cluster Study |
| Tennessee Valley Authority Interconnection Request 569 (Gas) | Gas | MS | 3.2 yrs | 620 MW | Interconnection study | Facility Study |
| ENTERGY MISSISSIPPI, LLC. Interconnection Request J3623 (Wind) | Wind (onshore) | MS | 2.4 yrs | 350 MW | Interconnection study | In Progress (unknown study) |
| Entergy Mississippi, LLC Interconnection Request E0031 (Gas) | Gas | MS | 1.1 yrs | 820 MW | Interconnection study | In Progress (unknown study) |
| Entergy Mississippi, LLC Interconnection Request E0047 (Gas) | Gas | MS | 1.1 yrs | 820 MW | Interconnection study | In Progress (unknown study) |
| ENTERGY MISSISSIPPI, LLC. Interconnection Request J4121 (Solar) | Solar | MS | 1.0 yrs | 300 MW | Interconnection study | — |
| Delta Blues Advanced Power Station (Unit 1A) | Gas | MS | — | 477 MW | Regulatory approvals pending | — |
| Delta Blues Advanced Power Station (Unit 1C) | Gas | MS | — | 342 MW | Regulatory approvals pending | — |
| South System Expansion 4 | Pipeline | MS | — | Not disclosed | Agency permitting | — |
| Kosciusko Junction Pipeline Project | Pipeline | MS | — | Not disclosed | Agency permitting | — |
| Kosciusko Junction Pipeline Project (Gulf South Pipeline Company, LLC ; Texas Gas Transmission. LLC) | Pipeline | MS | — | 1,180 MMcf/d | Agency permitting | — |
| Line 31 Expansion Project (Enbridge (Texas Eastern)) | Pipeline | MS | — | 125 MMcf/d | Agency permitting | — |
| South Mississippi Project (Energy Transfer) | Pipeline | TX,LA,MS | — | 2,000 MMcf/d | Planned, approvals not yet initiated | — |