Alabama energy projects waiting for approval

7 projects currently waiting on a permitting decision in Alabama, tracked live from public federal and state sources. See every state →

7
Projects
3,229 MW
Capacity waiting
1,256 MW
Clean energy capacity waiting
2/7 projects are zero-carbon generation
$5.64B
Est. investment waiting
6/7 projects have an applicable estimate
Documented estimates, not precise figures. See methodology.
7 projects
Project Fuel Location Waiting Capacity Stage Queue stage
COOSA RIVER (FERC No. P-2146)HydroAL21.1 yrs961 MWAgency permitting
Southern Company Interconnection Request 25-IC-1315 (Solar+Battery)SolarAL1.4 yrs295 MWInterconnection studyCluster Study
Southern Company Interconnection Request 25-IC-1382 (Gas)GasAL1.4 yrs707 MWInterconnection studyCluster Study
Tennessee Valley Authority Interconnection Request 25RSC-008 (Battery)StorageAL1.1 yrs300 MWInterconnection studyIn Progress (unknown study)
Tennessee Valley Authority Interconnection Request 25RSC-011 (Gas)GasAL1.1 yrs528 MWInterconnection studyIn Progress (unknown study)
Lowman Energy Center (Unit LEC3)GasAL438 MWRegulatory approvals pending
Hillabee Expansion Phase 3 (Transcontinental Gas Pipe Line Company, LLC)PipelineAL106 MMcf/dAgency permitting