generation · Wind (onshore)
WAPA Desert Southwest Region Interconnection Request 2024-G7 (Wind+Battery)
Yavapai, AZ
Capacity
313 MW
Waiting
1.8 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Grid region
West
Point of interconnection
Round Valley – Prescott 230 kV line
Estimated investment waiting
$536.9M
≈ 312,500 kW × $1,718/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.
Location
34.6311, -112.5772 — see the map for this project in context with others.
Public Hearings
Unknown
Hearing details: Unknown
Not available from this project’s data source yet. Check the sources below directly.
Sources
Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.