WAPA Desert Southwest Region Interconnection Request 2023-G9 (Solar+Battery)

La Paz, AZ

Capacity
250 MW
Waiting
3.2 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Grid region
West
Point of interconnection
Bouse 230kV Substation

Estimated investment waiting

$331.8M

250,000 kW × $1,327/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.

Location

33.7276, -114.0388 — see the map for this project in context with others.

Public Hearings

Unknown

Hearing details: Unknown

Not available from this project’s data source yet. Check the sources below directly.

Sources

Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.