generation · Solar

SDGE Interconnection Request 2207 (Solar+Battery)

Yuma, AZ

Capacity
500 MW
Waiting
3.4 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
Not Started
Grid region
CAISO
Point of interconnection
NORTH GILA - HOODOO WASH (SDGE Portion Only)
Queue cluster
Cluster 15

Estimated investment waiting

$663.5M

500,000 kW × $1,327/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.

Location

32.7739, -113.9109 — see the map for this project in context with others.

Public Hearings

Unknown

Hearing details: Unknown

Not available from this project’s data source yet. Check the sources below directly.

Sources

Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.