SCE Interconnection Request 2351 (Gas+Battery)

San Bernardino, CA

Capacity
300 MW
Waiting
3.4 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
Not Started
Grid region
CAISO
Point of interconnection
LUGO 500 kV
Queue cluster
Cluster 15

Estimated investment waiting

$394.8M

300,000 kW × $1,316/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.

Location

34.8567, -116.1816 — see the map for this project in context with others.

Public Hearings

Unknown

Hearing details: Unknown

Not available from this project’s data source yet. Check the sources below directly.

Sources

Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.