Capacity
423 MW
Waiting
2.6 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Grid region
West
Point of interconnection
Pinal West-Jojoba 500 kV Line
Queue cluster
Cluster 24
Estimated investment waiting
$561.6M
≈ 423,200 kW × $1,327/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.
Location
33.3452, -112.4989 — see the map for this project in context with others.
Public Hearings
Unknown
Hearing details: Unknown
Not available from this project’s data source yet. Check the sources below directly.
Sources
Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.